BEARING,ROLLER,CYL,1ROW,NU313-2Z

Material 4100001428 · BEARING · Plant 1000

CReorderNormalSlow-moving
Material
4100001428
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~55 days; expected demand during lead time 0.2.
  • 3.A 97.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 3.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 2 now.
Proposed purchase requisition
2 EA
Rp 2.8M · order by 01 Oct 2026
Expected arrival ≈ 55 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
3
order qty 2
Service level
97.9%
stockout risk now 2%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 198 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 15.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~23 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1850
C4 PRODUCT PUMP
C141.47
PX_KT-202
TURBINE FOR KC-202
S142.81

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
21 Feb 2026LowPX_PP-1850Overhaul PP-1850
09 Jan 2026MediumPX_KT-202KT-202 governor valve hunting
26 Nov 2025MediumPX_PP-1850PP-1850 discharge pressure low
01 Nov 2025MediumPX_PP-1850Leak from packing
17 Sept 2025MediumPX_KT-202Replace lamp as per PM finding
06 Jul 2025LowPX_KT-202KT-202 steam leak at gland
12 May 2025MediumPX_PP-1850Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
17 Mar 20261205000038799Other maintenance