BEARING,ROLLER,CYL,1ROW,7210BDB

Material 4100002235 · BEARING · Plant 1000

AMonitorInsurance gap
Material
4100002235
Category
BEARING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 0.2 EA/year: 0.2 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~55 days; expected demand during lead time 0.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
100.0%
stockout risk now 3%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 84.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 2 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_PP-1630-M
MOTOR FOR PP-1630
C400.19

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026LowPX_KC-717Leak from packing
08 Aug 2026MediumPX_KC-717Repair insulation KC-717
20 Jul 2026LowPX_KC-717Inspect coupling KC-717
05 Jul 2026MediumPX_KC-717Overhaul
12 Mar 2026LowPX_KC-717Replace lamp as per PM finding
01 Mar 2026MediumPX_KC-717Leak from packing
15 Nov 2025LowPX_KC-717Leak from packing
19 Aug 2025MediumPX_KC-717Repair insulation KC-717
18 May 2025LowPX_KC-717Overhaul

Recent goods issues

Never issued in the 17-month history.