SEAL,MECHANICAL,TYPE ZV470,PTFE
Material 4100005137 · SEAL · Plant 1000
ALong-leadReduceExcess
- Material
- 4100005137
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (24 of 31 FuncLocs A/B)
- Supplier
- ANUGRAH INSTRUMEN SENTOSA PT
- Lead time
- 141 d · P80 200 d
- Unit price
- Rp 35.8M
Recommendation
- 1.Forecast 11 SET/year: 9.3 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
- 2.Lead time ~141 days; expected demand during lead time 4.3 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 16.
- 4.Stock 61 exceeds the level to keep (16) by 45.
- 5.Long lead time: 80% of deliveries took up to 200 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 31 FuncLoc(s), 24 of them criticality A/B.
- 7.ML early warning: 48% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
61 / 1
next delivery 13 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 9
Rec. Max
16
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 35.8M
PO history
ML early warning: 48% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 10 days ago, 20 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 6 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 10.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 31 functional locations
24 with criticality A/B · 36 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1864 FUEL OIL PUMP | A | 1 | 6 | 2.33 |
| PX_PP-1735 SPENT CAUSTIC PUMP | A | 1 | 4 | 1.47 |
| PX_PP-408B METHANE PUMP | A | 1 | 4 | 1.90 |
| PX_PP-1022 QUENCH WATER PUMP | A | 1 | 3 | 1.47 |
| PX_PP-292 ETHYLENE PUMP | A | 1 | 3 | 1.05 |
| UT_PP-641A PROPYLENE PUMP | A | 1 | 3 | 1.05 |
| PX_PP-807B INHIBITOR PUMP | A | 1 | 2 | 1.05 |
| PX_PP-1033 CAUSTIC PUMP | A | 1 | 0 | 0.19 |
| PX_PP-489A RICH AMINE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1718 PROPYLENE PUMP | B | 1 | 12 | 4.04 |
| PX_PP-1070B FUEL OIL PUMP | B | 1 | 8 | 2.76 |
| PX_PP-1434 SPENT CAUSTIC PUMP | B | 1 | 4 | 1.90 |
Lead time and procurement
Lead time 141 ± 74 days (PO history, 4 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 10 Aug 2026 | PR10 Other | 1 | Rp 35.9M | 13 Oct 2026 open | 64 d |
| 19 Dec 2025 | PR01 Import / long-lead | 1 | Rp 34.5M | 24 Jun 2026 | 187 d |
| 17 Dec 2025 | PR06 Regular replenishment | 2 | Rp 35.8M | 22 Feb 2026 | 67 d |
| 21 May 2025 | PR04 Regular (other) | 2 | Rp 36.0M | 26 Dec 2025 | 219 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Dec 2026 | PX_PP-1106A | Pump overhaul | 0.72 |
| 01 Mar 2027 | PX_PP-807B | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_PP-1864 | Install scaffolding at PP-1864 |
| 27 Sept 2026 | Medium | PX_PP-807B | Replace bearing PP-807B |
| 24 Sept 2026 | Low | PX_PP-1106A | Replace bearing PP-1106A |
| 22 Sept 2026 | Emergency | PX_PP-1718 | Install scaffolding at PP-1718 |
| 19 Sept 2026 | Medium | PX_PP-1070B | Leak from packing |
| 18 Sept 2026 | Medium | PX_PP-1718 | Replace bearing PP-1718 |
| 16 Sept 2026 | Medium | UT_PP-641A | Replace lamp as per PM finding |
| 03 Sept 2026 | Medium | PX_PP-1070B | Repair insulation PP-1070B |
| 01 Sept 2026 | Low | PX_PP-1434 | PP-1434 discharge pressure low |
| 27 Aug 2026 | Medium | PX_PP-1718 | Install scaffolding at PP-1718 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Sept 2026 | 1 | 201000023715 | Corrective |
| 11 Aug 2026 | 1 | 201000005848 | Corrective |
| 02 Nov 2025 | 4 | 201000008924 | Corrective |
| 03 Oct 2025 | 1 | 201000016291 | Corrective |
| 02 Oct 2025 | 1 | 201000016291 | Corrective |
| 03 Jul 2025 | 1 | 201000006950 | Corrective |