SEAL,MECHANICAL,TYPE ZV470,PTFE

Material 4100005137 · SEAL · Plant 1000

ALong-leadReduceExcess
Material
4100005137
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (24 of 31 FuncLocs A/B)
Supplier
ANUGRAH INSTRUMEN SENTOSA PT
Lead time
141 d · P80 200 d
Unit price
Rp 35.8M

Recommendation

  • 1.Forecast 11 SET/year: 9.3 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 2.Lead time ~141 days; expected demand during lead time 4.3 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 16.
  • 4.Stock 61 exceeds the level to keep (16) by 45.
  • 5.Long lead time: 80% of deliveries took up to 200 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 31 FuncLoc(s), 24 of them criticality A/B.
  • 7.ML early warning: 48% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemSingle sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
61 / 1
next delivery 13 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 9
Rec. Max
16
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 35.8M
PO history
ML early warning: 48% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 10 days ago, 20 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 10.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 31 functional locations

24 with criticality A/B · 36 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1864
FUEL OIL PUMP
A162.33
PX_PP-1735
SPENT CAUSTIC PUMP
A141.47
PX_PP-408B
METHANE PUMP
A141.90
PX_PP-1022
QUENCH WATER PUMP
A131.47
PX_PP-292
ETHYLENE PUMP
A131.05
UT_PP-641A
PROPYLENE PUMP
A131.05
PX_PP-807B
INHIBITOR PUMP
A121.05
PX_PP-1033
CAUSTIC PUMP
A100.19
PX_PP-489A
RICH AMINE PUMP
A100.19
PX_PP-1718
PROPYLENE PUMP
B1124.04
PX_PP-1070B
FUEL OIL PUMP
B182.76
PX_PP-1434
SPENT CAUSTIC PUMP
B141.90

Lead time and procurement

Lead time 141 ± 74 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
10 Aug 2026PR10
Other
1Rp 35.9M13 Oct 2026
open
64 d
19 Dec 2025PR01
Import / long-lead
1Rp 34.5M24 Jun 2026187 d
17 Dec 2025PR06
Regular replenishment
2Rp 35.8M22 Feb 202667 d
21 May 2025PR04
Regular (other)
2Rp 36.0M26 Dec 2025219 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PP-1106APump overhaul0.72
01 Mar 2027PX_PP-807BPump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1864Install scaffolding at PP-1864
27 Sept 2026MediumPX_PP-807BReplace bearing PP-807B
24 Sept 2026LowPX_PP-1106AReplace bearing PP-1106A
22 Sept 2026EmergencyPX_PP-1718Install scaffolding at PP-1718
19 Sept 2026MediumPX_PP-1070BLeak from packing
18 Sept 2026MediumPX_PP-1718Replace bearing PP-1718
16 Sept 2026MediumUT_PP-641AReplace lamp as per PM finding
03 Sept 2026MediumPX_PP-1070BRepair insulation PP-1070B
01 Sept 2026LowPX_PP-1434PP-1434 discharge pressure low
27 Aug 2026MediumPX_PP-1718Install scaffolding at PP-1718

Recent goods issues

Posting dateQtyOrderOrder type
21 Sept 20261201000023715Corrective
11 Aug 20261201000005848Corrective
02 Nov 20254201000008924Corrective
03 Oct 20251201000016291Corrective
02 Oct 20251201000016291Corrective
03 Jul 20251201000006950Corrective