SEAL,MECHANICAL,SIZE DB790,NBR

Material 4100005265 · SEAL · Plant 1000

ALong-leadReorderCriticalBelow reorder point
Material
4100005265
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (7 of 9 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
142 d · P80 175 d
Unit price
Rp 31.6M

Recommendation

  • 1.Forecast 5.2 SET/year: 5.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~142 days; expected demand during lead time 2.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 10.
  • 4.On hand 2 + on order 2 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 175 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 9 FuncLoc(s), 7 of them criticality A/B.
Proposed purchase requisition
6 SET
Rp 189.9M · order by 01 Oct 2026
Expected arrival ≈ 142 days
Long-leadSingle sourceOpen PO
On hand / on order
2 / 2
next delivery 22 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 6
Rec. Max
10
order qty 2
Service level
100.0%
stockout risk now 5%
Unit price
Rp 31.6M
PO history
ML early warning: 24% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 1 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 9 functional locations

7 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1729A
COOLING WATER PUMP
A1217.90
PX_PP-1506
FEED PUMP
A172.76
PX_PP-1634A
QUENCH OIL PUMP
A110.19
PX_PP-1604A
DILUTION STEAM PUMP
A100.19
PX_PP-570
METHANOL PUMP
B1124.90
PX_PP-306A
BFW PUMP
B110.19
PX_PP-1751A
BFW PUMP
B100.19
PX_PP-217
RICH AMINE PUMP
C141.47
PX_PP-1706A
LEAN AMINE PUMP
C300.19

Lead time and procurement

Lead time 142 ± 67 days (PO history, 3 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
14 May 2026PR03
Regular replenishment
2Rp 30.5M22 Oct 2026
open
161 d
12 Nov 2025PR03
Regular replenishment
2Rp 31.6M16 May 2026185 d
15 Oct 2025PR03
Regular replenishment
1Rp 32.6M09 Dec 202555 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1506Replace bearing PP-1506
27 Sept 2026MediumPX_PP-1729AInstall scaffolding at PP-1729A
20 Sept 2026LowPX_PP-1729A[MSI-B-26-TCT-349] Permanent repair
12 Sept 2026MediumPX_PP-570PP-570 discharge pressure low
28 Aug 2026EmergencyPX_PP-1729AInstall scaffolding at PP-1729A
11 Aug 2026MediumPX_PP-1729APP-1729A seal leak
22 Jul 2026MediumPX_PP-570Install scaffolding at PP-570
17 Jul 2026LowPX_PP-1506PP-1506 seal leak
29 Jun 2026MediumPX_PP-217Overhaul PP-217
29 Jun 2026MediumPX_PP-570Replace bearing PP-570

Recent goods issues

Posting dateQtyOrderOrder type
30 Sept 20261201000021867Corrective
17 Jul 20261201000026330Corrective
24 Nov 20251201000019604Corrective
16 Nov 20251201000005641Corrective
18 Aug 20251204000009401Preventive