SEAL,MECHANICAL,MODEL BN65,MONEL

Material 4100005289 · SEAL · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100005289
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (13 of 15 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
147 d · P80 167 d
Unit price
Rp 98.2M

Recommendation

  • 1.Forecast 3.3 SET/year: 3.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~147 days; expected demand during lead time 1.3.
  • 3.A 98.1% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Long lead time: 80% of deliveries took up to 167 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 15 FuncLoc(s), 13 of them criticality A/B.
Proposed purchase requisition
3 SET
Rp 294.7M · order by 01 Oct 2026
Expected arrival ≈ 147 days
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
6
order qty 2
Service level
98.1%
stockout risk now 8%
Unit price
Rp 98.2M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 264 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 15 functional locations

13 with criticality A/B · 16 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1121
DILUTION STEAM PUMP
A120.62
PX_PP-1909A
QUENCH WATER PUMP
A110.19
PX_PP-1604A
DILUTION STEAM PUMP
A100.19
PX_PP-1809B
SEAL OIL PUMP
A100.19
PX_PP-992B
REFLUX PUMP
B183.19
PX_PP-121B
REFLUX PUMP
B241.05
PX_PP-1577D
ETHYLENE PUMP
B121.05
PX_PP-958B
SEAL OIL PUMP
B120.62
PX_PP-210A
HYDROGEN PUMP
B110.19
PX_PP-306A
BFW PUMP
B110.19
PX_PP-1751A
BFW PUMP
B100.19
PX_PP-1969B
FEED PUMP
B100.19

Lead time and procurement

Lead time 147 ± 58 days (PO history, 5 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
04 Mar 2026PR03
Regular replenishment
1Rp 95.9M26 Jul 2026144 d
16 Dec 2025PR03
Regular replenishment
1Rp 98.2M03 Aug 2026230 d
15 Sept 2025PR03
Regular replenishment
1Rp 100.1M02 Jan 2026109 d
14 Sept 2025PR03
Regular replenishment
2Rp 97.4M12 Feb 2026151 d
29 Jun 2025PR06
Regular replenishment
2Rp 101.5M29 Sept 202592 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
07 Sept 2026MediumPX_PP-1577DReplace bearing PP-1577D
06 Sept 2026MediumPX_PP-992BPP-992B discharge pressure low
05 Sept 2026MediumPX_PP-121BPP-121B discharge pressure low
26 Aug 2026MediumPX_PP-1121Oil leak at PP-1121 bearing housing
24 Aug 2026MediumPX_PP-121BInstall scaffolding at PP-121B
22 Aug 2026MediumPX_PP-958BPP-958B discharge pressure low
05 Aug 2026MediumPY_PP-1869Install cover plate for MCP cracking
21 May 2026MediumPX_PP-992BReplace lamp as per PM finding
30 Apr 2026MediumPX_PP-992BReplace lamp as per PM finding
20 Dec 2025MediumPX_PP-992BPP-992B seal leak

Recent goods issues

Posting dateQtyOrderOrder type
10 Jan 20262201000025650Corrective
23 Dec 20251201000015848Corrective
15 Nov 20251201000005641Corrective