SEAL,MECHANICAL,TYPE QR746,NBR

Material 4100005293 · SEAL · Plant 1000

AMaintainCritical insurance spare
Material
4100005293
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (6 of 7 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 0.2 SET/year: 0.2 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~150 days; expected demand during lead time 0.1.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 7 FuncLoc(s), 6 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 292.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 7 functional locations

6 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-412
REFLUX PUMP
A131.05
PX_PP-310C
RECYCLE ETHANE PUMP
A110.62
PX_PP-1325
BFW PUMP
B151.90
PX_PP-1448B
ETHYLENE PUMP
B110.62
PX_PP-500B
C3 RECYCLE PUMP
B100.19
PX_PP-724
METHANE PUMP
B100.19
PX_PP-376
DILUTION STEAM PUMP
C100.19

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_PP-412Oil leak at PP-412 bearing housing
17 Aug 2026MediumPX_PP-1325Oil leak at PP-1325 bearing housing
17 Apr 2026MediumPX_PP-412Replace bearing PP-412
07 Mar 2026MediumPX_PP-1325Replace bearing PP-1325
06 Mar 2026HighPX_PP-1325Oil leak at PP-1325 bearing housing
01 Sept 2025MediumPX_PP-1325Leak from packing
23 Jul 2025LowPX_PP-310CPP-310C discharge pressure low
21 Jun 2025MediumPX_PP-1448BPP-1448B abnormal noise
23 May 2025HighPX_PP-1325Leak from packing
19 May 2025MediumPX_PP-412Oil leak at PP-412 bearing housing

Recent goods issues

Never issued in the 17-month history.