SEAL,MECHANICAL,SIZE AD634,SS304

Material 4100005298 · SEAL · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100005298
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (9 of 11 FuncLocs A/B)
Supplier
BERKAH TEKNIK GLOBAL PT
Lead time
121 d · P80 213 d
Unit price
Rp 154.9M

Recommendation

  • 1.Forecast 6.6 SET/year: 3.1 unplanned (credibility blend: own history + installed-base prior) + 3.6 from the maintenance plan.
  • 2.Lead time ~121 days; expected demand during lead time 3.9 (incl. 2.9 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 9.
  • 4.On hand 4 + on order 0 is at or below the reorder point: order 5 now.
  • 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 11 FuncLoc(s), 9 of them criticality A/B.
Proposed purchase requisition
5 SET
Rp 774.7M · order by 01 Oct 2026
Expected arrival ≈ 121 days
Long-leadSingle sourcePlanned demand in lead time
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 5
Rec. Max
9
order qty 1
Service level
99.9%
stockout risk now 27%
Unit price
Rp 154.9M
PO history
ML early warning: 20% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 216 days ago, 8 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 11 functional locations

9 with criticality A/B · 16 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-167
GASOLINE PUMP
A152.33
PX_PP-500
GASOLINE PUMP
A431.05
PX_PP-1194
FEED PUMP
A121.05
PX_PP-251C
RICH AMINE PUMP
A121.05
PX_PP-592
FLUSHING OIL PUMP
A110.19
PX_PP-1323
DILUTION STEAM PUMP
A300.19
PX_PP-1805A
SEAL OIL PUMP
A100.19
PX_PP-601
DEMIN WATER PUMP
B172.33
PX_PP-1728
SEAL OIL PUMP
B121.05
PX_PP-1106A
LUBE OIL PUMP
C162.33
PX_PP-319
QUENCH OIL PUMP
S100.19

Lead time and procurement

Lead time 121 ± 65 days (PO history + category, 2 PO lines) · on-time 31%

PR dateTypeQtyUnit priceDeliveryLead time
26 Nov 2025PR06
Regular replenishment
2Rp 154.8M17 Jan 202652 d
27 Aug 2025PR06
Regular replenishment
1Rp 155.1M06 Dec 2025101 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PP-1106APump overhaul0.72
01 Jan 2027PX_PP-1323Pump overhaul2.15
02 Mar 2027PX_PP-167Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_PP-1106AReplace bearing PP-1106A
25 Aug 2026MediumPX_PP-1106APP-1106A high vibration
22 Aug 2026MediumPX_PP-601Replace bearing PP-601
06 Aug 2026MediumPX_PP-1106AOverhaul PP-1106A
04 Aug 2026MediumPX_PP-601PP-601 high vibration
01 Aug 2026LowPX_PP-1106APP-1106A discharge pressure low
27 Jul 2026MediumPX_PP-167Replace bearing PP-167
23 Jul 2026HighPX_PP-601Repair insulation PP-601
19 Jun 2026MediumPX_PP-1106APP-1106A seal leak
06 Apr 2026LowPX_PP-500Replace bearing PP-500

Recent goods issues

Posting dateQtyOrderOrder type
27 Feb 20261201000012359Corrective
19 Jul 20251201000005396Corrective