SEAL,MECHANICAL,SIZE AD634,SS304
Material 4100005298 · SEAL · Plant 1000
ALong-leadReorderNormalSlow-moving
- Material
- 4100005298
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (9 of 11 FuncLocs A/B)
- Supplier
- BERKAH TEKNIK GLOBAL PT
- Lead time
- 121 d · P80 213 d
- Unit price
- Rp 154.9M
Recommendation
- 1.Forecast 6.6 SET/year: 3.1 unplanned (credibility blend: own history + installed-base prior) + 3.6 from the maintenance plan.
- 2.Lead time ~121 days; expected demand during lead time 3.9 (incl. 2.9 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 9.
- 4.On hand 4 + on order 0 is at or below the reorder point: order 5 now.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 11 FuncLoc(s), 9 of them criticality A/B.
Proposed purchase requisition
5 SET
Rp 774.7M · order by 01 Oct 2026
Expected arrival ≈ 121 days
Long-leadSingle sourcePlanned demand in lead time
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 5
Rec. Max
9
order qty 1
Service level
99.9%
stockout risk now 27%
Unit price
Rp 154.9M
PO history
ML early warning: 20% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 216 days ago, 8 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 11 functional locations
9 with criticality A/B · 16 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-167 GASOLINE PUMP | A | 1 | 5 | 2.33 |
| PX_PP-500 GASOLINE PUMP | A | 4 | 3 | 1.05 |
| PX_PP-1194 FEED PUMP | A | 1 | 2 | 1.05 |
| PX_PP-251C RICH AMINE PUMP | A | 1 | 2 | 1.05 |
| PX_PP-592 FLUSHING OIL PUMP | A | 1 | 1 | 0.19 |
| PX_PP-1323 DILUTION STEAM PUMP | A | 3 | 0 | 0.19 |
| PX_PP-1805A SEAL OIL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-601 DEMIN WATER PUMP | B | 1 | 7 | 2.33 |
| PX_PP-1728 SEAL OIL PUMP | B | 1 | 2 | 1.05 |
| PX_PP-1106A LUBE OIL PUMP | C | 1 | 6 | 2.33 |
| PX_PP-319 QUENCH OIL PUMP | S | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 121 ± 65 days (PO history + category, 2 PO lines) · on-time 31%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 26 Nov 2025 | PR06 Regular replenishment | 2 | Rp 154.8M | 17 Jan 2026 | 52 d |
| 27 Aug 2025 | PR06 Regular replenishment | 1 | Rp 155.1M | 06 Dec 2025 | 101 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Dec 2026 | PX_PP-1106A | Pump overhaul | 0.72 |
| 01 Jan 2027 | PX_PP-1323 | Pump overhaul | 2.15 |
| 02 Mar 2027 | PX_PP-167 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_PP-1106A | Replace bearing PP-1106A |
| 25 Aug 2026 | Medium | PX_PP-1106A | PP-1106A high vibration |
| 22 Aug 2026 | Medium | PX_PP-601 | Replace bearing PP-601 |
| 06 Aug 2026 | Medium | PX_PP-1106A | Overhaul PP-1106A |
| 04 Aug 2026 | Medium | PX_PP-601 | PP-601 high vibration |
| 01 Aug 2026 | Low | PX_PP-1106A | PP-1106A discharge pressure low |
| 27 Jul 2026 | Medium | PX_PP-167 | Replace bearing PP-167 |
| 23 Jul 2026 | High | PX_PP-601 | Repair insulation PP-601 |
| 19 Jun 2026 | Medium | PX_PP-1106A | PP-1106A seal leak |
| 06 Apr 2026 | Low | PX_PP-500 | Replace bearing PP-500 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 27 Feb 2026 | 1 | 201000012359 | Corrective |
| 19 Jul 2025 | 1 | 201000005396 | Corrective |