SEAL,MECHANICAL,TYPE CJ726,NBR
Material 4100005330 · SEAL · Plant 1000
ALong-leadReorderNormalSlow-moving
- Material
- 4100005330
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 136 d · P80 213 d
- Unit price
- Rp 34.3M
Recommendation
- 1.Forecast 3.8 SET/year: 3.1 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~136 days; expected demand during lead time 1.9 (incl. 0.7 planned).
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 9.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 7 now.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
7 SET
Rp 240.4M · order by 01 Oct 2026
Expected arrival ≈ 136 days
Long-leadSingle sourcePlanned demand in lead time
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
9
order qty 2
Service level
99.7%
stockout risk now 44%
Unit price
Rp 34.3M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 302 days ago, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 5 functional locations
3 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-556A LEAN AMINE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1299 QUENCH OIL PUMP | B | 1 | 1 | 0.62 |
| PX_PP-1168A SEAL OIL PUMP | B | 1 | 0 | 0.19 |
| PX_PP-244A LEAN AMINE PUMP | C | 1 | 7 | 2.33 |
| PX_PP-1850 C4 PRODUCT PUMP | C | 1 | 4 | 1.47 |
Lead time and procurement
Lead time 136 ± 65 days (PO history + category, 2 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 17 Mar 2026 | PR03 Regular replenishment | 2 | Rp 34.1M | 05 Aug 2026 | 141 d |
| 07 Feb 2026 | PR03 Regular replenishment | 2 | Rp 34.6M | 09 May 2026 | 91 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_PP-556A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 16 Sept 2026 | Medium | PX_PP-244A | Oil leak at PP-244A bearing housing |
| 19 Apr 2026 | Low | PX_PP-244A | Replace lamp as per PM finding |
| 21 Feb 2026 | Low | PX_PP-1850 | Overhaul PP-1850 |
| 25 Jan 2026 | Medium | PX_PP-244A | Overhaul PP-244A |
| 09 Dec 2025 | High | PX_PP-244A | Replace lamp as per PM finding |
| 26 Nov 2025 | Medium | PX_PP-1850 | PP-1850 discharge pressure low |
| 01 Nov 2025 | Medium | PX_PP-1850 | Leak from packing |
| 18 Sept 2025 | Medium | PX_PP-244A | Oil leak at PP-244A bearing housing |
| 04 Sept 2025 | Medium | PX_PP-244A | Install scaffolding at PP-244A |
| 05 Jun 2025 | Low | PX_PP-1299 | Overhaul PP-1299 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Dec 2025 | 2 | 201000008508 | Corrective |