Sparely
DU

SEAL,MECHANICAL,TYPE CJ726,NBR

Material 4100005330 · SEAL · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100005330
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
136 d · P80 213 d
Unit price
Rp 34.3M

Recommendation

  • 1.Forecast 3.8 SET/year: 3.1 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~136 days; expected demand during lead time 1.9 (incl. 0.7 planned).
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 9.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 7 now.
  • 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
7 SET
Rp 240.4M · order by 01 Oct 2026
Expected arrival ≈ 136 days
Long-leadSingle sourcePlanned demand in lead time
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
9
order qty 2
Service level
99.7%
stockout risk now 44%
Unit price
Rp 34.3M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 302 days ago, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 5 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-556A
LEAN AMINE PUMP
A100.19
PX_PP-1299
QUENCH OIL PUMP
B110.62
PX_PP-1168A
SEAL OIL PUMP
B100.19
PX_PP-244A
LEAN AMINE PUMP
C172.33
PX_PP-1850
C4 PRODUCT PUMP
C141.47

Lead time and procurement

Lead time 136 ± 65 days (PO history + category, 2 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
17 Mar 2026PR03
Regular replenishment
2Rp 34.1M05 Aug 2026141 d
07 Feb 2026PR03
Regular replenishment
2Rp 34.6M09 May 202691 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_PP-556APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
16 Sept 2026MediumPX_PP-244AOil leak at PP-244A bearing housing
19 Apr 2026LowPX_PP-244AReplace lamp as per PM finding
21 Feb 2026LowPX_PP-1850Overhaul PP-1850
25 Jan 2026MediumPX_PP-244AOverhaul PP-244A
09 Dec 2025HighPX_PP-244AReplace lamp as per PM finding
26 Nov 2025MediumPX_PP-1850PP-1850 discharge pressure low
01 Nov 2025MediumPX_PP-1850Leak from packing
18 Sept 2025MediumPX_PP-244AOil leak at PP-244A bearing housing
04 Sept 2025MediumPX_PP-244AInstall scaffolding at PP-244A
05 Jun 2025LowPX_PP-1299Overhaul PP-1299

Recent goods issues

Posting dateQtyOrderOrder type
03 Dec 20252201000008508Corrective