SEAL,MECHANICAL,TYPE AM52,A105

Material 4100005416 · SEAL · Plant 1000

AMaintainCritical insurance spare
Material
4100005416
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (4 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~150 days; expected demand during lead time 0.1.
  • 3.A 94.3% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
4 / 11
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
94.3%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 216.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 5 functional locations

4 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-103
COOLING WATER PUMP
A172.33
PX_PP-1194B
RICH AMINE PUMP
A100.19
PX_PP-958B
SEAL OIL PUMP
B120.62
PX_PP-210A
HYDROGEN PUMP
B110.19
PX_PP-1546A
FUEL OIL PUMP
C100.19

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_PP-103Oil leak at PP-103 bearing housing
24 Sept 2026MediumPX_PP-103PP-103 abnormal noise
22 Aug 2026MediumPX_PP-958BPP-958B discharge pressure low
10 Jan 2026MediumPX_PP-103PP-103 seal leak
19 Nov 2025EmergencyPX_PP-103Install scaffolding at PP-103
22 Oct 2025MediumPX_PP-103[MSI-B-25-WHU-395] Permanent repair
06 Sept 2025MediumPX_PP-103PP-103 seal leak
25 May 2025MediumPX_PP-103Install scaffolding at PP-103
21 May 2025MediumPX_PP-958BInstall scaffolding at PP-958B
11 May 2025HighPX_PP-210ALeak from packing

Recent goods issues

Never issued in the 17-month history.