SEAL,MECHANICAL,SIZE BX108,GRAPHITE

Material 4100005469 · SEAL · Plant 1000

AReorderCriticalStockout
Material
4100005469
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (2 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 0.8 SET/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 2 now.
  • 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
2 SET
Rp 189.2M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Convert to Stock ItemPrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 5%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 178.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 4 functional locations

2 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1049
PROPYLENE PUMP
A100.19
PX_PP-1728
SEAL OIL PUMP
B121.05
PX_PP-1941A
QUENCH OIL PUMP
S131.47
PX_PP-319
QUENCH OIL PUMP
S100.19

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Jun 2027PX_PP-1941APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
14 Sept 2026MediumPX_PP-1941AReplace lamp as per PM finding
06 Jul 2026MediumPX_PP-1941AReplace lamp as per PM finding
20 Dec 2025MediumPX_PP-1728PP-1728 abnormal noise
19 Jul 2025MediumPX_PP-1728Leak from packing
11 Jun 2025MediumPX_PP-1941A[MSI-B-25-BJE-225] Permanent repair

Recent goods issues

Never issued in the 17-month history.