SEAL,MECHANICAL,TYPE WL931,CS

Material 4100005491 · SEAL · Plant 1000

CReduceSlow-moving
Material
4100005491
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
C (0 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 4.1 SET/year: 1.3 unplanned (credibility blend: own history + installed-base prior) + 2.9 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 0.5.
  • 3.A 90.4% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Stock 5 exceeds the level to keep (2) by 3.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
90.4%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 203 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 37.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~71 days.

Installed on 3 functional locations

0 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1470A
METHANE PUMP
C131.05
PX_PP-1872A
QUENCH WATER PUMP
S141.90
PX_PP-1007A
METHANE PUMP
S430.62

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Jun 2027PX_PP-1007APump overhaul2.86

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_PP-1470AReplace lamp as per PM finding
25 Aug 2026MediumPX_PP-1872AOil leak at PP-1872A bearing housing
25 Jul 2026MediumPX_PP-1007APP-1007A discharge pressure low
29 Apr 2026MediumPX_PP-1872APP-1872A discharge pressure low
04 Mar 2026MediumPX_PP-1470AOil leak at PP-1470A bearing housing
03 Dec 2025MediumPX_PP-1007AInstall scaffolding at PP-1007A
17 Sept 2025LowPX_PP-1872AReplace lamp as per PM finding
27 Jul 2025MediumPX_PP-1007AInstall scaffolding at PP-1007A
14 Jun 2025LowPX_PP-1872AOil leak at PP-1872A bearing housing
17 May 2025MediumPX_PP-1470AInstall cover plate for MCP cracking

Recent goods issues

Posting dateQtyOrderOrder type
12 Mar 20261201000023936Corrective
27 May 20251205000034719Other maintenance