Sparely
DU

SEAL,MECHANICAL,TYPE EQ517,MONEL

Material 4100005608 · SEAL · Plant 1000

AReorderNormalSlow-moving
Material
4100005608
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (3 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 1.3 SET/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~150 days; expected demand during lead time 0.5.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
3 SET
Rp 283.8M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.8%
stockout risk now 10%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 403 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 3 functional locations

3 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PP-1056
QUENCH WATER PUMP
A131.05
PX_PP-987A
INHIBITOR PUMP
A121.05
PX_PP-1434
SPENT CAUSTIC PUMP
B141.90

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_PP-1434PP-1434 discharge pressure low
23 Aug 2026MediumPX_PP-1434PP-1434 abnormal noise
14 Aug 2026MediumPX_PP-1434Replace lamp as per PM finding
17 Dec 2025HighPY_PP-1056[MSI-B-25-SWZ-286] Permanent repair
22 Sept 2025MediumPY_PP-1056PP-1056 abnormal noise
01 Aug 2025MediumPX_PP-987AReplace lamp as per PM finding
09 Jul 2025HighPX_PP-1434PP-1434 seal leak
09 Jul 2025MediumPX_PP-987APP-987A abnormal noise
13 May 2025LowPY_PP-1056Oil leak at PP-1056 bearing housing

Recent goods issues

Posting dateQtyOrderOrder type
24 Aug 20251201000033690Corrective