SEAL,MECHANICAL,SIZE UU499,NBR

Material 4100005648 · SEAL · Plant 1000

BLong-leadMonitorSlow-moving
Material
4100005648
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
154 d · P80 181 d
Unit price
Rp 57.3M

Recommendation

  • 1.Forecast 1.0 SET/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~154 days; expected demand during lead time 0.4.
  • 3.A 96.8% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.Long lead time: 80% of deliveries took up to 181 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
96.8%
stockout risk now 0%
Unit price
Rp 57.3M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 251 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 249.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~71 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PP-1131
REFLUX PUMP
B100.19

Lead time and procurement

Lead time 154 ± 45 days (PO history, 4 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
01 May 2026PR03
Regular replenishment
1Rp 57.5M28 Aug 2026119 d
26 Sept 2025PR03
Regular replenishment
2Rp 57.5M26 Mar 2026181 d
03 Aug 2025PR03
Regular replenishment
2Rp 57.0M30 Dec 2025149 d
29 Jun 2025PR03
Regular replenishment
1Rp 57.1M27 Dec 2025181 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
23 Jan 20262201000023958Corrective
22 Jan 20261201000023958Corrective