SEAL,MECHANICAL,TYPE WS434,A105
Material 4100005693 · SEAL · Plant 1000
ALong-leadMonitorInsurance gap
- Material
- 4100005693
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- GEMILANG SUPLINDO SENTOSA PT
- Lead time
- 137 d · P80 213 d
- Unit price
- Rp 53.3M
Recommendation
- 1.Forecast 0.0 SET/year: 0.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~137 days; expected demand during lead time 0.0.
- 3.A 98.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidateLong-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.8%
stockout risk now 1%
Unit price
Rp 53.3M
PO history
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 49.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-703B REFLUX PUMP | A | 1 | 2 | 0.62 |
| PX_PP-1049 PROPYLENE PUMP | A | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 137 ± 65 days (PO history + category, 1 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 07 Jun 2026 | PR06 Regular replenishment | 1 | Rp 53.3M | 12 Sept 2026 | 97 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 06 Nov 2025 | Low | PX_PP-703B | PP-703B discharge pressure low |
| 04 May 2025 | Medium | PX_PP-703B | PP-703B abnormal noise |
Recent goods issues
Never issued in the 17-month history.