SEAL,MECHANICAL,SIZE UP305,CS
Material 4100005704 · SEAL · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100005704
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 94.6M (est.)
Recommendation
- 1.Forecast 2.1 SET/year: 1.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~150 days; expected demand during lead time 0.6.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 2 now.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
2 SET
Rp 189.2M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.7%
stockout risk now 2%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 312 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1752A SLOP OIL PUMP | A | 1 | 4 | 1.90 |
| PX_PP-1498C CHARGE GAS PUMP | B | 1 | 5 | 1.90 |
| PX_PP-720 ETHYLENE PUMP | C | 1 | 1 | 0.62 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Jul 2027 | PX_PP-1498C | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 07 Sept 2026 | Low | PX_PP-1752A | [MSI-B-26-XYL-202] Permanent repair |
| 25 Aug 2026 | Low | PX_PP-1498C | [MSI-B-26-LAH-309/M] Replace line |
| 22 Jul 2026 | High | PX_PP-1498C | Install scaffolding at PP-1498C |
| 16 Jun 2026 | Medium | PX_PP-1498C | Overhaul PP-1498C |
| 28 Apr 2026 | Medium | PX_PP-1498C | Oil leak at PP-1498C bearing housing |
| 30 Jan 2026 | Low | PX_PP-1752A | Replace bearing PP-1752A |
| 19 Nov 2025 | Low | PX_PP-1752A | [MSI-B-25-DGU-132] Permanent repair |
| 28 Jul 2025 | Low | PX_PP-1752A | Replace lamp as per PM finding |
| 29 Jun 2025 | Medium | PX_PP-1498C | Replace bearing PP-1498C |
| 07 Jun 2025 | Low | PX_PP-720 | Oil leak at PP-720 bearing housing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 23 Nov 2025 | 1 | 201000009792 | Corrective |