SEAL,MECHANICAL,MODEL YJ232,PTFE
Material 4100005834 · SEAL · Plant 1000
CReduceNon-moving
- Material
- 4100005834
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- C (0 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 94.6M (est.)
Recommendation
- 1.Forecast 0.8 SET/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~150 days; expected demand during lead time 0.1.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
- 4.Stock 163 exceeds the level to keep (0) by 163.
Convert to Non StockPrice estimatedLead time estimated
On hand / on order
163 / 0
no open PO
Today Min / Max
5 / 16
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~71 days.
Installed on 3 functional locations
0 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-244A LEAN AMINE PUMP | C | 1 | 7 | 2.33 |
| PX_PP-536 HYDROGEN PUMP | C | 1 | 0 | 0.19 |
| PX_PP-439B CONDENSATE PUMP | S | 1 | 2 | 0.62 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Aug 2027 | PX_PP-536 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 16 Sept 2026 | Medium | PX_PP-244A | Oil leak at PP-244A bearing housing |
| 19 Apr 2026 | Low | PX_PP-244A | Replace lamp as per PM finding |
| 25 Jan 2026 | Medium | PX_PP-244A | Overhaul PP-244A |
| 09 Dec 2025 | High | PX_PP-244A | Replace lamp as per PM finding |
| 28 Nov 2025 | Medium | PX_PP-439B | [MSI-B-25-KFB-167] Permanent repair |
| 18 Sept 2025 | Medium | PX_PP-244A | Oil leak at PP-244A bearing housing |
| 04 Sept 2025 | Medium | PX_PP-244A | Install scaffolding at PP-244A |
| 31 May 2025 | Medium | PX_PP-244A | Overhaul PP-244A |
| 20 May 2025 | Low | PX_PP-439B | PP-439B high vibration |
Recent goods issues
Never issued in the 17-month history.