SEAL,MECHANICAL,TYPE SR281,SS316
Material 4100005862 · SEAL · Plant 1000
BReduceNon-moving
- Material
- 4100005862
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- B (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 94.6M (est.)
Recommendation
- 1.Forecast 0.9 SET/year: 0.2 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~150 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Stock 26 exceeds the level to keep (3) by 23.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
26 / 0
no open PO
Today Min / Max
10 / 21
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 68.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~71 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-785A DILUTION STEAM PUMP | B | 1 | 5 | 1.90 |
| PX_PP-376A QUENCH OIL PUMP | C | 1 | 1 | 0.62 |
| PX_PP-1872A QUENCH WATER PUMP | S | 1 | 4 | 1.90 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Feb 2027 | PX_PP-376A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Aug 2026 | Medium | PX_PP-1872A | Oil leak at PP-1872A bearing housing |
| 25 Jul 2026 | Medium | PX_PP-785A | [MSI-B-26-DPX-213/M] Replace line |
| 18 Jun 2026 | Emergency | PX_PP-785A | PP-785A abnormal noise |
| 29 Apr 2026 | Medium | PX_PP-1872A | PP-1872A discharge pressure low |
| 12 Jan 2026 | Medium | PX_PP-785A | PP-785A discharge pressure low |
| 17 Sept 2025 | Low | PX_PP-1872A | Replace lamp as per PM finding |
| 03 Aug 2025 | High | PX_PP-785A | [MSI-B-25-ZHN-181] Permanent repair |
| 24 Jun 2025 | Low | PX_PP-376A | PP-376A seal leak |
| 14 Jun 2025 | Low | PX_PP-1872A | Oil leak at PP-1872A bearing housing |
| 24 May 2025 | Medium | PX_PP-785A | [MSI-B-25-GXA-247/M] Replace line |
Recent goods issues
Never issued in the 17-month history.