SEAL,MECHANICAL,MODEL AW550,MONEL
Material 4100006048 · SEAL · Plant 1000
AReduceNon-moving
- Material
- 4100006048
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (4 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 94.6M (est.)
Recommendation
- 1.Forecast 0.9 SET/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~150 days; expected demand during lead time 0.1.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Stock 4 exceeds the level to keep (2) by 2.
- 5.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
3 / 7
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 204.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 4 functional locations
4 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-779A LUBE OIL PUMP | A | 1 | 2 | 0.62 |
| PX_PP-1541 DEMIN WATER PUMP | A | 1 | 0 | 0.19 |
| PX_PP-785A DILUTION STEAM PUMP | B | 1 | 5 | 1.90 |
| PX_PP-1299 QUENCH OIL PUMP | B | 1 | 1 | 0.62 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Jun 2027 | PX_PP-1541 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Jul 2026 | Medium | PX_PP-785A | [MSI-B-26-DPX-213/M] Replace line |
| 18 Jun 2026 | Emergency | PX_PP-785A | PP-785A abnormal noise |
| 29 Apr 2026 | Medium | PX_PP-779A | Replace bearing PP-779A |
| 12 Jan 2026 | Medium | PX_PP-785A | PP-785A discharge pressure low |
| 03 Aug 2025 | High | PX_PP-785A | [MSI-B-25-ZHN-181] Permanent repair |
| 05 Jun 2025 | Low | PX_PP-1299 | Overhaul PP-1299 |
| 24 May 2025 | Medium | PX_PP-785A | [MSI-B-25-GXA-247/M] Replace line |
| 05 May 2025 | Medium | PX_PP-779A | PP-779A abnormal noise |
Recent goods issues
Never issued in the 17-month history.