SEAL,MECHANICAL,SIZE NX293,MONEL

Material 4100006557 · SEAL · Plant 1000

AReduceNon-moving
Material
4100006557
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (3 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~150 days; expected demand during lead time 0.1.
  • 3.A 94.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 3 exceeds the level to keep (1) by 2.
  • 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
3 / 4
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
94.9%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 193.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 3 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-739
ETHYLENE PUMP
A100.19
PX_PP-1807C
C3 RECYCLE PUMP
B161.47
PX_PP-1399
LUBE OIL PUMP
B341.47

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Aug 2026MediumPX_PP-1399Install scaffolding at PP-1399
09 Jun 2026HighPX_PP-1399Replace bearing PP-1399
12 May 2026MediumPX_PP-1807CInstall scaffolding at PP-1807C
18 Apr 2026MediumPX_PP-1399Repair insulation PP-1399
24 Jan 2026MediumPX_PP-1807CReplace lamp as per PM finding
07 Nov 2025MediumPX_PP-1807COverhaul PP-1807C
19 Sept 2025MediumPX_PP-1807CInstall scaffolding at PP-1807C
30 Aug 2025MediumPX_PP-1807CPP-1807C abnormal noise
20 Jul 2025MediumPX_PP-1399Replace lamp as per PM finding
23 May 2025MediumPX_PP-1807CReplace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.