IMPELLER,SIZE QM224,A105

Material 4100006904 · IMPELLER · Plant 1000

AReorderCriticalStockout
Material
4100006904
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
A (17 of 22 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 14 EA/year: 11 unplanned (credibility blend: own history + installed-base prior) + 2.9 from the maintenance plan.
  • 2.Lead time ~184 days; expected demand during lead time 7.7 (incl. 2.1 planned).
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 19, order up to 21.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 21 now.
  • 5.Installed on 22 FuncLoc(s), 17 of them criticality A/B.
Proposed purchase requisition
21 EA
Rp 2.1B · order by 01 Oct 2026
Expected arrival ≈ 184 days
Needs Management sign-off before it reaches the PR draft
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
19
safety stock 12
Rec. Max
21
order qty 2
Service level
99.8%
stockout risk now 100%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 305 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 12.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 22 functional locations

17 with criticality A/B · 33 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-888A
CONDENSATE PUMP
A161.90
PX_PP-1651
BFW PUMP
A141.05
PX_PP-957A
C3 RECYCLE PUMP
A331.05
PX_PP-1991A
FEED PUMP
A120.62
PX_PP-744B
RICH AMINE PUMP
A321.05
PX_PP-779A
LUBE OIL PUMP
A120.62
PX_PP-638A
BOTTOM PUMP
A110.19
PX_PP-645C
LUBE OIL PUMP
A110.19
PX_PP-1101A
REFLUX PUMP
A300.19
PX_PP-1115
SLOP OIL PUMP
A100.19
PX_PP-1809B
SEAL OIL PUMP
A100.19
PX_PP-891C
CHARGE GAS PUMP
A300.19

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
09 Jan 2027PX_PP-957APump overhaul2.15
02 Jul 2027PX_PP-135APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1892BReplace lamp as per PM finding
23 Sept 2026MediumPX_PP-1892BPP-1892B abnormal noise
22 Sept 2026MediumPX_PP-888AOil leak at PP-888A bearing housing
03 Sept 2026LowPX_PP-820A[MSI-B-26-WPE-117] Permanent repair
01 Sept 2026LowPX_PP-1434PP-1434 discharge pressure low
23 Aug 2026MediumPX_PP-1434PP-1434 abnormal noise
17 Aug 2026MediumPX_PP-1325Oil leak at PP-1325 bearing housing
16 Aug 2026HighPX_PP-888APP-888A abnormal noise
14 Aug 2026MediumPX_PP-1434Replace lamp as per PM finding
08 Aug 2026MediumPY_PP-490PP-490 high vibration

Recent goods issues

Posting dateQtyOrderOrder type
30 Nov 20252201000032005Corrective