IMPELLER,SIZE QM224,A105
Material 4100006904 · IMPELLER · Plant 1000
AReorderCriticalStockout
- Material
- 4100006904
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (17 of 22 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 184 d · P80 276 d
- Unit price
- Rp 102.1M (est.)
Recommendation
- 1.Forecast 14 EA/year: 11 unplanned (credibility blend: own history + installed-base prior) + 2.9 from the maintenance plan.
- 2.Lead time ~184 days; expected demand during lead time 7.7 (incl. 2.1 planned).
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 19, order up to 21.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 21 now.
- 5.Installed on 22 FuncLoc(s), 17 of them criticality A/B.
Proposed purchase requisition
21 EA
Rp 2.1B · order by 01 Oct 2026
Expected arrival ≈ 184 days
Needs Management sign-off before it reaches the PR draft
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
19
safety stock 12
Rec. Max
21
order qty 2
Service level
99.8%
stockout risk now 100%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 305 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 12.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 22 functional locations
17 with criticality A/B · 33 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-888A CONDENSATE PUMP | A | 1 | 6 | 1.90 |
| PX_PP-1651 BFW PUMP | A | 1 | 4 | 1.05 |
| PX_PP-957A C3 RECYCLE PUMP | A | 3 | 3 | 1.05 |
| PX_PP-1991A FEED PUMP | A | 1 | 2 | 0.62 |
| PX_PP-744B RICH AMINE PUMP | A | 3 | 2 | 1.05 |
| PX_PP-779A LUBE OIL PUMP | A | 1 | 2 | 0.62 |
| PX_PP-638A BOTTOM PUMP | A | 1 | 1 | 0.19 |
| PX_PP-645C LUBE OIL PUMP | A | 1 | 1 | 0.19 |
| PX_PP-1101A REFLUX PUMP | A | 3 | 0 | 0.19 |
| PX_PP-1115 SLOP OIL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1809B SEAL OIL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-891C CHARGE GAS PUMP | A | 3 | 0 | 0.19 |
Lead time and procurement
Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 09 Jan 2027 | PX_PP-957A | Pump overhaul | 2.15 |
| 02 Jul 2027 | PX_PP-135A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_PP-1892B | Replace lamp as per PM finding |
| 23 Sept 2026 | Medium | PX_PP-1892B | PP-1892B abnormal noise |
| 22 Sept 2026 | Medium | PX_PP-888A | Oil leak at PP-888A bearing housing |
| 03 Sept 2026 | Low | PX_PP-820A | [MSI-B-26-WPE-117] Permanent repair |
| 01 Sept 2026 | Low | PX_PP-1434 | PP-1434 discharge pressure low |
| 23 Aug 2026 | Medium | PX_PP-1434 | PP-1434 abnormal noise |
| 17 Aug 2026 | Medium | PX_PP-1325 | Oil leak at PP-1325 bearing housing |
| 16 Aug 2026 | High | PX_PP-888A | PP-888A abnormal noise |
| 14 Aug 2026 | Medium | PX_PP-1434 | Replace lamp as per PM finding |
| 08 Aug 2026 | Medium | PY_PP-490 | PP-490 high vibration |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Nov 2025 | 2 | 201000032005 | Corrective |