IMPELLER,SIZE TH244,INCOLOY

Material 4100006926 · IMPELLER · Plant 1000

ALong-leadReorderCriticalBelow reorder point
Material
4100006926
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 10 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
238 d · P80 311 d
Unit price
Rp 164.5M

Recommendation

  • 1.Forecast 6.0 EA/year: 6.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~238 days; expected demand during lead time 3.9.
  • 3.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 12.
  • 4.On hand 2 + on order 4 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 311 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 10 FuncLoc(s), 7 of them criticality A/B.
  • 7.ML early warning: 34% probability of demand in the next 90 days.
Proposed purchase requisition
6 EA
Rp 987.2M · order by 01 Oct 2026
Expected arrival ≈ 238 days
Long-leadML early warningSingle sourceOpen PO
On hand / on order
2 / 4
next delivery 30 Apr 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 7
Rec. Max
12
order qty 2
Service level
98.9%
stockout risk now 21%
Unit price
Rp 164.5M
PO history
ML early warning: 34% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 110 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 10 functional locations

7 with criticality A/B · 10 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-703B
REFLUX PUMP
A120.62
PX_PP-1865A
METHANOL PUMP
A100.19
PX_PP-442A
CAUSTIC PUMP
A100.19
PX_PP-390B
SLOP OIL PUMP
B1197.04
PX_PP-367C
METHANE PUMP
B141.90
PX_PP-866A
METHANE PUMP
B141.90
PX_PP-154A
CONDENSATE PUMP
B120.62
PX_PP-1782A
BFW PUMP
C120.62
PX_PP-247B
C3 RECYCLE PUMP
C110.62
PX_PP-953A
INHIBITOR PUMP
C100.19

Lead time and procurement

Lead time 238 ± 63 days (PO history, 3 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
02 Aug 2026PR03
Regular replenishment
2Rp 165.3M04 Jul 2027
open
336 d
20 Oct 2025PR03
Regular replenishment
2Rp 159.6M30 Apr 2027
open
557 d
07 Oct 2025PR03
Regular replenishment
1Rp 163.7M07 Jul 2026273 d
16 Aug 2025PR06
Regular replenishment
2Rp 166.3M08 May 2026265 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Sept 2026LowPX_PP-390BPP-390B high vibration
25 Aug 2026MediumPX_PP-390BPP-390B seal leak
21 Aug 2026MediumPX_PP-390BInstall scaffolding at PP-390B
13 Aug 2026MediumPX_PP-390BOil leak at PP-390B bearing housing
13 Jun 2026MediumPX_PP-154ALeak from packing
08 May 2026LowPX_PP-390BPainting PP-390B
23 Apr 2026MediumPX_PP-390B[MSI-B-26-UER-253/M] Replace line
21 Apr 2026EmergencyPX_PP-367COil leak at PP-367C bearing housing
10 Apr 2026MediumPX_PP-390BOil leak at PP-390B bearing housing
26 Mar 2026LowPX_PP-367CReplace bearing PP-367C

Recent goods issues

Posting dateQtyOrderOrder type
13 Jun 20261201000013076Corrective
16 Jan 20262201000036064Corrective
29 Sept 20252201000005438Corrective