Sparely
DU

IMPELLER,SIZE SZ712,SS316

Material 4100006929 · IMPELLER · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100006929
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 5 FuncLocs A/B)
Supplier
PRIMA ELEKTRIK ABADI PT
Lead time
169 d · P80 276 d
Unit price
Rp 39.5M

Recommendation

  • 1.Forecast 2.1 EA/year: 1.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~169 days; expected demand during lead time 1.4 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 6.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 276 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 236.8M · order by 01 Oct 2026
Expected arrival ≈ 169 days
Long-leadSingle sourcePlanned demand in lead time
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
6
order qty 1
Service level
99.9%
stockout risk now 100%
Unit price
Rp 39.5M
PO history
ML early warning: 13% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 67 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 5 functional locations

4 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-326A
INHIBITOR PUMP
A131.47
PX_PP-1775A
GASOLINE PUMP
A120.62
PX_PP-1323
DILUTION STEAM PUMP
A100.19
PX_PP-1025B
CAUSTIC PUMP
B131.05
PX_PP-705
METHANOL PUMP
S100.19

Lead time and procurement

Lead time 169 ± 88 days (PO history + category, 1 PO lines) · on-time 30%

PR dateTypeQtyUnit priceDeliveryLead time
28 Aug 2025PR03
Regular replenishment
1Rp 39.5M31 Dec 2025125 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Jan 2027PX_PP-1323Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Aug 2026MediumPX_PP-1775APP-1775A discharge pressure low
03 Apr 2026MediumPX_PP-326AReplace lamp as per PM finding
08 Dec 2025MediumPX_PP-326ARepair insulation PP-326A
18 Sept 2025MediumPX_PP-1025BOverhaul PP-1025B
15 Sept 2025MediumPX_PP-1025BOverhaul PP-1025B
17 Jul 2025MediumPX_PP-326APP-326A seal leak
24 May 2025MediumPX_PP-1775AReplace lamp as per PM finding
21 May 2025MediumPX_PP-1025BPP-1025B high vibration

Recent goods issues

Posting dateQtyOrderOrder type
26 Jul 20261201000010816Corrective