IMPELLER,TYPE EM55,SS316

Material 4100006979 · IMPELLER · Plant 1000

AReorderCriticalStockout
Material
4100006979
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~184 days; expected demand during lead time 0.8.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 510.5M · order by 01 Oct 2026
Expected arrival ≈ 184 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
5
order qty 1
Service level
99.9%
stockout risk now 54%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 251 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 4 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1890
BFW PUMP
A151.47
PX_PP-745
FEED PUMP
B172.76
PX_PP-1678A
METHANE PUMP
B110.19
PX_PP-1141D
DILUTION STEAM PUMP
C100.19

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
07 Sept 2026MediumPX_PP-1890PP-1890 discharge pressure low
08 Aug 2026MediumPX_PP-745PP-745 high vibration
03 Aug 2026LowPX_PP-1890Painting PP-1890
08 Jun 2026EmergencyPX_PP-745[MSI-B-26-YAH-100/M] Replace line
13 May 2026LowPX_PP-745Leak from packing
23 Mar 2026EmergencyPX_PP-1890Leak from packing
06 Feb 2026LowPX_PP-745Repair insulation PP-745
20 Nov 2025MediumPX_PP-745Install cover plate for MCP cracking
25 Oct 2025MediumPX_PP-1890PP-1890 discharge pressure low
19 Oct 2025LowPX_PP-745Oil leak at PP-745 bearing housing

Recent goods issues

Posting dateQtyOrderOrder type
23 Jan 20261201000023882Corrective