IMPELLER,TYPE AW676,SS304
Material 4100007009 · IMPELLER · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100007009
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- LANGIT ELEKTRIK ABADI PT
- Lead time
- 160 d · P80 161 d
- Unit price
- Rp 202.3M
Recommendation
- 1.Forecast 2.5 EA/year: 2.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~160 days; expected demand during lead time 1.1.
- 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 7 now.
- 5.Long lead time: 80% of deliveries took up to 161 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
7 EA
Rp 1.4B · order by 01 Oct 2026
Expected arrival ≈ 160 days
Needs Management sign-off before it reaches the PR draft
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
7
order qty 2
Service level
99.3%
stockout risk now 52%
Unit price
Rp 202.3M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 214 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| UT_PP-818B RICH AMINE PUMP | A | 1 | 12 | 4.90 |
Lead time and procurement
Lead time 160 ± 65 days (PO history, 3 PO lines) · on-time 46%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 28 Jan 2026 | PR04 Regular (other) | 2 | Rp 204.1M | 15 Jul 2026 | 168 d |
| 28 Aug 2025 | PR06 Regular replenishment | 1 | Rp 202.3M | 26 Jan 2026 | 151 d |
| 02 Jun 2025 | PR06 Regular replenishment | 2 | Rp 201.6M | 27 Aug 2025 | 86 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | UT_PP-818B | Replace lamp as per PM finding |
| 05 Sept 2026 | Low | UT_PP-818B | PP-818B seal leak |
| 18 Jun 2026 | Medium | UT_PP-818B | Oil leak at PP-818B bearing housing |
| 24 Apr 2026 | Medium | UT_PP-818B | Replace bearing PP-818B |
| 08 Apr 2026 | High | UT_PP-818B | PP-818B abnormal noise |
| 24 Mar 2026 | Medium | UT_PP-818B | PP-818B abnormal noise |
| 01 Mar 2026 | Medium | UT_PP-818B | PP-818B seal leak |
| 03 Feb 2026 | Low | UT_PP-818B | Repair insulation PP-818B |
| 22 Dec 2025 | Low | UT_PP-818B | PP-818B high vibration |
| 08 Dec 2025 | Low | UT_PP-818B | PP-818B discharge pressure low |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 01 Mar 2026 | 1 | 201000014462 | Corrective |
| 12 Dec 2025 | 2 | 201000001564 | Corrective |