IMPELLER,TYPE AW676,SS304

Material 4100007009 · IMPELLER · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100007009
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
LANGIT ELEKTRIK ABADI PT
Lead time
160 d · P80 161 d
Unit price
Rp 202.3M

Recommendation

  • 1.Forecast 2.5 EA/year: 2.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~160 days; expected demand during lead time 1.1.
  • 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 7 now.
  • 5.Long lead time: 80% of deliveries took up to 161 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
7 EA
Rp 1.4B · order by 01 Oct 2026
Expected arrival ≈ 160 days
Needs Management sign-off before it reaches the PR draft
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
7
order qty 2
Service level
99.3%
stockout risk now 52%
Unit price
Rp 202.3M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 214 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
UT_PP-818B
RICH AMINE PUMP
A1124.90

Lead time and procurement

Lead time 160 ± 65 days (PO history, 3 PO lines) · on-time 46%

PR dateTypeQtyUnit priceDeliveryLead time
28 Jan 2026PR04
Regular (other)
2Rp 204.1M15 Jul 2026168 d
28 Aug 2025PR06
Regular replenishment
1Rp 202.3M26 Jan 2026151 d
02 Jun 2025PR06
Regular replenishment
2Rp 201.6M27 Aug 202586 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowUT_PP-818BReplace lamp as per PM finding
05 Sept 2026LowUT_PP-818BPP-818B seal leak
18 Jun 2026MediumUT_PP-818BOil leak at PP-818B bearing housing
24 Apr 2026MediumUT_PP-818BReplace bearing PP-818B
08 Apr 2026HighUT_PP-818BPP-818B abnormal noise
24 Mar 2026MediumUT_PP-818BPP-818B abnormal noise
01 Mar 2026MediumUT_PP-818BPP-818B seal leak
03 Feb 2026LowUT_PP-818BRepair insulation PP-818B
22 Dec 2025LowUT_PP-818BPP-818B high vibration
08 Dec 2025LowUT_PP-818BPP-818B discharge pressure low

Recent goods issues

Posting dateQtyOrderOrder type
01 Mar 20261201000014462Corrective
12 Dec 20252201000001564Corrective