IMPELLER,SIZE GS324,INCOLOY

Material 4100007316 · IMPELLER · Plant 1000

CMaintainNo stock needed
Material
4100007316
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 1.1 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~184 days; expected demand during lead time 0.9 (incl. 0.7 planned).
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Convert to Non StockPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 100%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 129 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 16.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~105 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1744
PROPYLENE PUMP
C100.19

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PX_PP-1744Pump overhaul0.72

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
25 May 20261201000010896Corrective