IMPELLER,SIZE TB815,NBR
Material 4100007317 · IMPELLER · Plant 1000
AMonitorInsurance gap
- Material
- 4100007317
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 184 d · P80 276 d
- Unit price
- Rp 102.1M (est.)
Recommendation
- 1.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~184 days; expected demand during lead time 0.0.
- 3.A 95.8% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
95.8%
stockout risk now 4%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 191.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-818 LUBE OIL PUMP | A | 1 | 6 | 1.90 |
| PY_PP-1374 C3 RECYCLE PUMP | B | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Aug 2026 | Medium | PX_PP-818 | Install scaffolding at PP-818 |
| 28 May 2026 | Medium | PX_PP-818 | PP-818 high vibration |
| 10 Apr 2026 | Medium | PX_PP-818 | PP-818 high vibration |
| 31 Oct 2025 | Medium | PX_PP-818 | PP-818 high vibration |
| 30 Sept 2025 | Medium | PX_PP-818 | Leak from packing |
| 15 May 2025 | Low | PX_PP-818 | PP-818 high vibration |
Recent goods issues
Never issued in the 17-month history.