IMPELLER,TYPE EP414,MONEL

Material 4100007346 · IMPELLER · Plant 1000

BLong-leadReorderCriticalStockout
Material
4100007346
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 2 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
212 d · P80 276 d
Unit price
Rp 205.5M

Recommendation

  • 1.Forecast 0.6 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~212 days; expected demand during lead time 0.3.
  • 3.A 95.2% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 0 + on order 1 is at or below the reorder point: order 1 now.
  • 5.Long lead time: 80% of deliveries took up to 276 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 205.5M · order by 01 Oct 2026
Expected arrival ≈ 212 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 22 Mar 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
95.2%
stockout risk now 5%
Unit price
Rp 205.5M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 204 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 336.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~105 days.

Installed on 2 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1886B
C4 PRODUCT PUMP
B100.19
PX_PP-1470A
METHANE PUMP
C231.05

Lead time and procurement

Lead time 212 ± 88 days (PO history + category, 1 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
01 Jun 2026PR06
Regular replenishment
1Rp 205.5M22 Mar 2027
open
294 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_PP-1470AReplace lamp as per PM finding
04 Mar 2026MediumPX_PP-1470AOil leak at PP-1470A bearing housing
17 May 2025MediumPX_PP-1470AInstall cover plate for MCP cracking

Recent goods issues

Posting dateQtyOrderOrder type
11 Mar 20261201000023936Corrective