IMPELLER,MODEL NZ509,PTFE
Material 4100007487 · IMPELLER · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100007487
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- GEMILANG SUPLINDO SENTOSA PT
- Lead time
- 174 d · P80 276 d
- Unit price
- Rp 99.5M
Recommendation
- 1.Forecast 1.7 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~174 days; expected demand during lead time 1.2 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
- 5.Long lead time: 80% of deliveries took up to 276 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 497.4M · order by 01 Oct 2026
Expected arrival ≈ 174 days
Long-leadConvert to Stock ItemSingle sourcePlanned demand in lead time
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
5
order qty 1
Service level
99.9%
stockout risk now 100%
Unit price
Rp 99.5M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 290 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 3 functional locations
2 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1250 METHANE PUMP | A | 1 | 4 | 1.90 |
| PX_PP-166A SPENT CAUSTIC PUMP | A | 2 | 1 | 0.19 |
| PX_PP-1366A C3 RECYCLE PUMP | S | 1 | 4 | 0.62 |
Lead time and procurement
Lead time 174 ± 88 days (PO history + category, 2 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 May 2026 | PR06 Regular replenishment | 1 | Rp 98.3M | 26 Sept 2026 | 127 d |
| 19 Jan 2026 | PR10 Other | 1 | Rp 100.7M | 31 Jul 2026 | 193 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Feb 2027 | PX_PP-1250 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Feb 2026 | Medium | PX_PP-1366A | PP-1366A high vibration |
| 26 Dec 2025 | Low | PX_PP-1366A | Install scaffolding at PP-1366A |
| 18 Dec 2025 | Low | PX_PP-1250 | PP-1250 high vibration |
| 16 Nov 2025 | High | PX_PP-1250 | Leak from packing |
| 13 Nov 2025 | Low | PX_PP-1366A | Painting PP-1366A |
| 20 Oct 2025 | Low | PX_PP-1250 | PP-1250 seal leak |
| 20 Jun 2025 | Medium | PX_PP-1250 | PP-1250 seal leak |
| 20 May 2025 | Medium | PX_PP-166A | Oil leak at PP-166A bearing housing |
| 19 May 2025 | Low | PX_PP-1366A | PP-1366A seal leak |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Dec 2025 | 1 | 201000006079 | Corrective |
| 30 Jun 2025 | 1 | 201000013463 | Corrective |