IMPELLER,TYPE QV277,SS304

Material 4100007688 · IMPELLER · Plant 1000

AReorderNormalCritical insurance spare
Material
4100007688
Category
IMPELLER
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
184 d · P80 276 d
Unit price
Rp 102.1M (est.)

Recommendation

  • 1.Forecast 0.9 EA/year: 0.2 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~184 days; expected demand during lead time 0.8 (incl. 0.7 planned).
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 1 now.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 102.1M · order by 01 Oct 2026
Expected arrival ≈ 184 days
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 343.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 4 functional locations

2 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-556A
LEAN AMINE PUMP
A100.19
PX_PP-812A
SEAL OIL PUMP
B131.05
PX_PP-224
QUENCH WATER PUMP
C100.19
PX_PP-1857B
SPENT CAUSTIC PUMP
S162.33

Lead time and procurement

Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_PP-556APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Sept 2026LowPX_PP-812APP-812A discharge pressure low
22 Aug 2026HighPX_PP-1857BPP-1857B discharge pressure low
12 Jun 2026LowPX_PP-1857BPP-1857B abnormal noise
20 Mar 2026MediumPX_PP-1857BOil leak at PP-1857B bearing housing
06 Jan 2026MediumPX_PP-1857BOverhaul PP-1857B
08 Dec 2025MediumPX_PP-812APainting PP-812A
11 Nov 2025HighPX_PP-1857BPP-1857B high vibration
19 Jun 2025MediumPX_PP-812AReplace lamp as per PM finding
24 May 2025MediumPX_PP-1857BPP-1857B abnormal noise

Recent goods issues

Never issued in the 17-month history.