IMPELLER,TYPE QV277,SS304
Material 4100007688 · IMPELLER · Plant 1000
AReorderNormalCritical insurance spare
- Material
- 4100007688
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 184 d · P80 276 d
- Unit price
- Rp 102.1M (est.)
Recommendation
- 1.Forecast 0.9 EA/year: 0.2 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~184 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 1 now.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 102.1M · order by 01 Oct 2026
Expected arrival ≈ 184 days
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.7%
stockout risk now 0%
Unit price
Rp 102.1M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 343.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 4 functional locations
2 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-556A LEAN AMINE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-812A SEAL OIL PUMP | B | 1 | 3 | 1.05 |
| PX_PP-224 QUENCH WATER PUMP | C | 1 | 0 | 0.19 |
| PX_PP-1857B SPENT CAUSTIC PUMP | S | 1 | 6 | 2.33 |
Lead time and procurement
Lead time 184 ± 88 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_PP-556A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 12 Sept 2026 | Low | PX_PP-812A | PP-812A discharge pressure low |
| 22 Aug 2026 | High | PX_PP-1857B | PP-1857B discharge pressure low |
| 12 Jun 2026 | Low | PX_PP-1857B | PP-1857B abnormal noise |
| 20 Mar 2026 | Medium | PX_PP-1857B | Oil leak at PP-1857B bearing housing |
| 06 Jan 2026 | Medium | PX_PP-1857B | Overhaul PP-1857B |
| 08 Dec 2025 | Medium | PX_PP-812A | Painting PP-812A |
| 11 Nov 2025 | High | PX_PP-1857B | PP-1857B high vibration |
| 19 Jun 2025 | Medium | PX_PP-812A | Replace lamp as per PM finding |
| 24 May 2025 | Medium | PX_PP-1857B | PP-1857B abnormal noise |
Recent goods issues
Never issued in the 17-month history.