IMPELLER,SIZE DM745,CS
Material 4100008223 · IMPELLER · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100008223
- Category
- IMPELLER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- MITRA PERKASA NUSANTARA PT
- Lead time
- 194 d · P80 276 d
- Unit price
- Rp 127.8M
Recommendation
- 1.Forecast 1.3 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~194 days; expected demand during lead time 0.7.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
- 5.Long lead time: 80% of deliveries took up to 276 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 511.2M · order by 01 Oct 2026
Expected arrival ≈ 194 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.5%
stockout risk now 49%
Unit price
Rp 127.8M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 1 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-103 COOLING WATER PUMP | A | 1 | 7 | 2.33 |
| PX_PP-1194B RICH AMINE PUMP | A | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 194 ± 88 days (PO history + category, 1 PO lines) · on-time 48%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 08 Jul 2025 | PR03 Regular replenishment | 2 | Rp 127.8M | 16 Feb 2026 | 223 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_PP-103 | Oil leak at PP-103 bearing housing |
| 24 Sept 2026 | Medium | PX_PP-103 | PP-103 abnormal noise |
| 10 Jan 2026 | Medium | PX_PP-103 | PP-103 seal leak |
| 19 Nov 2025 | Emergency | PX_PP-103 | Install scaffolding at PP-103 |
| 22 Oct 2025 | Medium | PX_PP-103 | [MSI-B-25-WHU-395] Permanent repair |
| 06 Sept 2025 | Medium | PX_PP-103 | PP-103 seal leak |
| 25 May 2025 | Medium | PX_PP-103 | Install scaffolding at PP-103 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 1 | 201000014601 | Corrective |