SLEEVE,SHAFT,TYPE NY787,A182F11
Material 4100008733 · SLEEVE · Plant 1000
ALong-leadReorderCriticalBelow reorder point
- Material
- 4100008733
- Category
- SLEEVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (19 of 23 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 196 d · P80 210 d
- Unit price
- Rp 25.4M
Recommendation
- 1.Forecast 7.5 EA/year: 6.8 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~196 days; expected demand during lead time 3.6.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 13.
- 4.On hand 1 + on order 3 is at or below the reorder point: order 9 now.
- 5.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 23 FuncLoc(s), 19 of them criticality A/B.
Proposed purchase requisition
9 EA
Rp 228.3M · order by 01 Oct 2026
Expected arrival ≈ 196 days
Long-leadSingle sourceOpen PO
On hand / on order
1 / 3
next delivery 16 Mar 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 7
Rec. Max
13
order qty 3
Service level
99.7%
stockout risk now 33%
Unit price
Rp 25.4M
PO history
ML early warning: 29% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 48 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 7.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~67 days.
Installed on 23 functional locations
19 with criticality A/B · 27 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1729A COOLING WATER PUMP | A | 2 | 21 | 7.90 |
| PX_PP-1460A SEAL OIL PUMP | A | 1 | 9 | 3.19 |
| PX_PP-1862 HYDROGEN PUMP | A | 1 | 5 | 1.47 |
| PX_PP-408B METHANE PUMP | A | 1 | 4 | 1.90 |
| PX_PP-1166B BFW PUMP | A | 1 | 2 | 0.62 |
| PX_PP-339C SLOP OIL PUMP | A | 1 | 1 | 0.19 |
| PX_PP-1099 LUBE OIL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1384B COOLING WATER PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1721A LUBE OIL PUMP | A | 4 | 0 | 0.19 |
| PX_PP-1809B SEAL OIL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-765B QUENCH OIL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-891C CHARGE GAS PUMP | A | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 196 ± 55 days (PO history + category, 2 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 18 Aug 2026 | PR03 Regular replenishment | 1 | Rp 25.0M | 04 Jun 2027 open | 290 d |
| 04 Jun 2026 | PR06 Regular replenishment | 2 | Rp 25.7M | 16 Mar 2027 open | 285 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Aug 2027 | PX_PP-536 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 Sept 2026 | Medium | PX_PP-1729A | Install scaffolding at PP-1729A |
| 20 Sept 2026 | Low | PX_PP-1729A | [MSI-B-26-TCT-349] Permanent repair |
| 12 Sept 2026 | Medium | PX_PP-479 | Install scaffolding at PP-479 |
| 05 Sept 2026 | Low | PX_PP-1899 | Painting PP-1899 |
| 28 Aug 2026 | Emergency | PX_PP-1729A | Install scaffolding at PP-1729A |
| 18 Aug 2026 | Medium | PX_PP-479 | Oil leak at PP-479 bearing housing |
| 11 Aug 2026 | Medium | PX_PP-1460A | PP-1460A seal leak |
| 11 Aug 2026 | Medium | PX_PP-1729A | PP-1729A seal leak |
| 01 Aug 2026 | Medium | PX_PP-408B | [MSI-B-26-NMP-200/M] Replace line |
| 13 Jul 2026 | Low | PX_PP-1460A | PP-1460A high vibration |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 14 Aug 2026 | 1 | 201000039930 | Corrective |
| 26 Jan 2026 | 1 | 201000001593 | Corrective |
| 22 Jan 2026 | 1 | 201000025721 | Corrective |
| 15 Sept 2025 | 2 | 201000039095 | Corrective |