SLEEVE,SHAFT,SIZE JT446,CS

Material 4100008783 · SLEEVE · Plant 1000

ALong-leadMonitorHealthy
Material
4100008783
Category
SLEEVE
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
147 d · P80 219 d
Unit price
Rp 22.5M

Recommendation

  • 1.Forecast 4.8 EA/year: 4.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~147 days; expected demand during lead time 1.9.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 12.
  • 4.Long lead time: 80% of deliveries took up to 219 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
  • 6.ML early warning: 55% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceOpen PO
On hand / on order
6 / 5
next delivery 04 Dec 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 9
Rec. Max
12
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 22.5M
PO history
ML early warning: 55% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 69 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~67 days.

Installed on 4 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1384B
COOLING WATER PUMP
A100.19
PY_PP-1063
METHANE PUMP
A100.19
PX_PP-912
BOTTOM PUMP
B220.62
PY_PP-203B
DEMIN WATER PUMP
S172.76

Lead time and procurement

Lead time 147 ± 65 days (PO history, 6 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
25 Aug 2026PR03
Regular replenishment
3Rp 23.2M01 Apr 2027
open
219 d
25 Aug 2026PR03
Regular replenishment
1Rp 22.7M04 Dec 2026
open
101 d
20 Jul 2026PR03
Regular replenishment
1Rp 22.2M16 Jan 2027
open
180 d
18 May 2026PR06
Regular replenishment
3Rp 22.2M12 Jul 202655 d
29 Jan 2026PR03
Regular replenishment
3Rp 22.0M07 Jun 2026129 d
26 Dec 2025PR03
Regular replenishment
2Rp 23.6M20 Aug 2026237 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Aug 2026MediumPY_PP-203BOverhaul PP-203B
14 Aug 2026MediumPY_PP-203BPP-203B high vibration
16 Jul 2026MediumPX_PP-912Replace bearing PP-912
09 Jul 2026MediumPY_PP-203BPainting PP-203B
17 Feb 2026MediumPY_PP-203B[MSI-B-26-FRN-294/M] Replace line
02 Dec 2025MediumPY_PP-203BReplace lamp as per PM finding
31 Oct 2025LowPY_PP-203B[MSI-B-25-HVK-154/M] Replace line
11 Jun 2025LowPY_PP-203BPP-203B seal leak
03 May 2025MediumPX_PP-912PP-912 abnormal noise

Recent goods issues

Posting dateQtyOrderOrder type
24 Jul 20262201000024842Corrective
14 Jul 20261201000006682Corrective
12 Nov 20253201000025430Corrective