SLEEVE,SHAFT,SIZE JT446,CS
Material 4100008783 · SLEEVE · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100008783
- Category
- SLEEVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- GEMILANG SUPLINDO SENTOSA PT
- Lead time
- 147 d · P80 219 d
- Unit price
- Rp 22.5M
Recommendation
- 1.Forecast 4.8 EA/year: 4.8 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~147 days; expected demand during lead time 1.9.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 12.
- 4.Long lead time: 80% of deliveries took up to 219 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
- 6.ML early warning: 55% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceOpen PO
On hand / on order
6 / 5
next delivery 04 Dec 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 9
Rec. Max
12
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 22.5M
PO history
ML early warning: 55% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 69 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~67 days.
Installed on 4 functional locations
3 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1384B COOLING WATER PUMP | A | 1 | 0 | 0.19 |
| PY_PP-1063 METHANE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-912 BOTTOM PUMP | B | 2 | 2 | 0.62 |
| PY_PP-203B DEMIN WATER PUMP | S | 1 | 7 | 2.76 |
Lead time and procurement
Lead time 147 ± 65 days (PO history, 6 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 25 Aug 2026 | PR03 Regular replenishment | 3 | Rp 23.2M | 01 Apr 2027 open | 219 d |
| 25 Aug 2026 | PR03 Regular replenishment | 1 | Rp 22.7M | 04 Dec 2026 open | 101 d |
| 20 Jul 2026 | PR03 Regular replenishment | 1 | Rp 22.2M | 16 Jan 2027 open | 180 d |
| 18 May 2026 | PR06 Regular replenishment | 3 | Rp 22.2M | 12 Jul 2026 | 55 d |
| 29 Jan 2026 | PR03 Regular replenishment | 3 | Rp 22.0M | 07 Jun 2026 | 129 d |
| 26 Dec 2025 | PR03 Regular replenishment | 2 | Rp 23.6M | 20 Aug 2026 | 237 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 17 Aug 2026 | Medium | PY_PP-203B | Overhaul PP-203B |
| 14 Aug 2026 | Medium | PY_PP-203B | PP-203B high vibration |
| 16 Jul 2026 | Medium | PX_PP-912 | Replace bearing PP-912 |
| 09 Jul 2026 | Medium | PY_PP-203B | Painting PP-203B |
| 17 Feb 2026 | Medium | PY_PP-203B | [MSI-B-26-FRN-294/M] Replace line |
| 02 Dec 2025 | Medium | PY_PP-203B | Replace lamp as per PM finding |
| 31 Oct 2025 | Low | PY_PP-203B | [MSI-B-25-HVK-154/M] Replace line |
| 11 Jun 2025 | Low | PY_PP-203B | PP-203B seal leak |
| 03 May 2025 | Medium | PX_PP-912 | PP-912 abnormal noise |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Jul 2026 | 2 | 201000024842 | Corrective |
| 14 Jul 2026 | 1 | 201000006682 | Corrective |
| 12 Nov 2025 | 3 | 201000025430 | Corrective |