SLEEVE,SHAFT,MODEL GY132,INCOLOY
Material 4100008803 · SLEEVE · Plant 1000
AReorderCriticalStockout
- Material
- 4100008803
- Category
- SLEEVE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (6 of 7 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 135 d · P80 210 d
- Unit price
- Rp 8.1M (est.)
Recommendation
- 1.Forecast 6.3 EA/year: 4.9 unplanned (credibility blend: own history + installed-base prior) + 1.4 from the maintenance plan.
- 2.Lead time ~135 days; expected demand during lead time 2.5 (incl. 0.7 planned).
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 15.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 15 now.
- 5.Installed on 7 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
15 EA
Rp 121.3M · order by 01 Oct 2026
Expected arrival ≈ 135 days
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 9
Rec. Max
15
order qty 4
Service level
100.0%
stockout risk now 100%
Unit price
Rp 8.1M
Category + unit estimate
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 78 days ago, 3 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~67 days.
Installed on 7 functional locations
6 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1864 FUEL OIL PUMP | A | 1 | 6 | 2.33 |
| PX_PP-283B BFW PUMP | A | 1 | 3 | 1.47 |
| PX_PP-556A LEAN AMINE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1498C CHARGE GAS PUMP | B | 1 | 5 | 1.90 |
| PX_PP-1928 FUEL OIL PUMP | B | 3 | 3 | 1.05 |
| PX_PP-1352 LUBE OIL PUMP | B | 1 | 0 | 0.19 |
| PX_PP-367A REFLUX PUMP | C | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 135 ± 55 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_PP-556A | Pump overhaul | 0.72 |
| 02 Jul 2027 | PX_PP-1498C | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_PP-1864 | Install scaffolding at PP-1864 |
| 03 Sept 2026 | Low | PX_PP-283B | Leak from packing |
| 25 Aug 2026 | Low | PX_PP-1498C | [MSI-B-26-LAH-309/M] Replace line |
| 22 Jul 2026 | High | PX_PP-1498C | Install scaffolding at PP-1498C |
| 08 Jul 2026 | High | PX_PP-1928 | PP-1928 discharge pressure low |
| 16 Jun 2026 | Medium | PX_PP-1498C | Overhaul PP-1498C |
| 28 Apr 2026 | Medium | PX_PP-1498C | Oil leak at PP-1498C bearing housing |
| 28 Apr 2026 | Medium | PX_PP-1864 | Install cover plate for MCP cracking |
| 04 Apr 2026 | Medium | PX_PP-1864 | Leak from packing |
| 15 Mar 2026 | Emergency | PX_PP-1864 | Overhaul PP-1864 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Jul 2026 | 1 | 201000006298 | Corrective |
| 03 Dec 2025 | 2 | 201000008508 | Corrective |
| 03 Dec 2025 | 1 | 201000008508 | Corrective |