Sparely
DU

SLEEVE,SHAFT,SIZE UL374,A105

Material 4100008854 · SLEEVE · Plant 1000

AReorderCriticalStockout
Material
4100008854
Category
SLEEVE
Base unit
EA
MRP type
Non Stock
Criticality
A (4 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
135 d · P80 210 d
Unit price
Rp 8.1M (est.)

Recommendation

  • 1.Forecast 0.8 EA/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~135 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 2 now.
  • 5.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
2 EA
Rp 16.2M · order by 01 Oct 2026
Expected arrival ≈ 135 days
Convert to Stock ItemPrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 4%
Unit price
Rp 8.1M
Category + unit estimate
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 144.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~67 days.

Installed on 4 functional locations

4 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PP-1056
QUENCH WATER PUMP
A131.05
PX_PP-807B
INHIBITOR PUMP
A121.05
PY_PP-835B
METHANE PUMP
A100.19
PX_PP-118B
CAUSTIC PUMP
B110.19

Lead time and procurement

Lead time 135 ± 55 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Mar 2027PX_PP-807BPump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Sept 2026MediumPX_PP-807BReplace bearing PP-807B
17 Dec 2025HighPY_PP-1056[MSI-B-25-SWZ-286] Permanent repair
22 Sept 2025MediumPY_PP-1056PP-1056 abnormal noise
05 Jul 2025LowPX_PP-807BReplace bearing PP-807B
24 May 2025MediumPX_PP-118BPSM25/Oil leak at PP-118B bearing housin
13 May 2025LowPY_PP-1056Oil leak at PP-1056 bearing housing

Recent goods issues

Never issued in the 17-month history.