SLEEVE,SHAFT,SIZE NP593,VITON

Material 4100009852 · SLEEVE · Plant 1000

BLong-leadReorderNormalBelow reorder point
Material
4100009852
Category
SLEEVE
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
PRIMA ELEKTRIK ABADI PT
Lead time
167 d · P80 210 d
Unit price
Rp 21.2M

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~167 days; expected demand during lead time 0.2.
  • 3.A 98.3% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 1 now.
  • 5.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 67 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 21.2M · order by 01 Oct 2026
Expected arrival ≈ 167 days
Long-leadSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.3%
stockout risk now 2%
Unit price
Rp 21.2M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 98 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 152.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1939
BFW PUMP
B100.19

Lead time and procurement

Lead time 167 ± 55 days (PO history + category, 1 PO lines) · on-time 30%

PR dateTypeQtyUnit priceDeliveryLead time
10 Dec 2025PR05
Project / turnaround
2Rp 21.2M28 Aug 2026261 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
25 Jun 20261201000038239Corrective