Sparely
DU

COUPLING,TYPE RS556,INCOLOY

Material 4100010543 · COUPLING · Plant 1000

ALong-leadReorderCriticalSlow-moving
Material
4100010543
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
A (17 of 23 FuncLocs A/B)
Supplier
MITRA SARANA INTERNASIONAL PT
Lead time
77 d · P80 139 d
Unit price
Rp 5.6M

Recommendation

  • 1.Forecast 8.5 SET/year: 8.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~77 days; expected demand during lead time 1.8.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 12.
  • 4.On hand 1 + on order 2 is at or below the reorder point: order 9 now.
  • 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 23 FuncLoc(s), 17 of them criticality A/B.
  • 7.ML early warning: 50% probability of demand in the next 90 days.
Proposed purchase requisition
9 SET
Rp 50.3M · order by 01 Oct 2026
Expected arrival ≈ 77 days
Long-leadML early warningSingle sourceOpen PO
On hand / on order
1 / 2
next delivery 22 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
12
order qty 5
Service level
99.9%
stockout risk now 11%
Unit price
Rp 5.6M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 488 days ago, 15 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 23 functional locations

17 with criticality A/B · 27 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_KC-419A
PROPYLENE FAN
A1195.71
PX_KC-536A
LUBE OIL BLOWER
A1114.42
PX_KC-316D
METHANOL FAN
A251.43
PX_KC-778A
CONDENSATE COMPRESSOR
A131.43
PX_PP-1478B
CONDENSATE PUMP
A121.05
PX_PP-1575A
METHANE PUMP
A110.19
PY_KC-636C
SLOP OIL COMPRESSOR
A110.57
PX_KC-621
SEAL OIL FAN
A100.57
PX_KC-225D
INHIBITOR COMPRESSOR
B192.71
PX_PP-1807C
C3 RECYCLE PUMP
B161.47
PX_KC-620A
DEMIN WATER AIR COMPRESSOR
B121.00
PX_PP-1543
DILUTION STEAM PUMP
B120.62

Lead time and procurement

Lead time 77 ± 54 days (PO history + category, 2 PO lines) · on-time 34%

PR dateTypeQtyUnit priceDeliveryLead time
12 Sept 2026PR06
Regular replenishment
1Rp 5.4M10 Nov 2026
open
59 d
14 Aug 2026PR06
Regular replenishment
1Rp 5.7M22 Oct 2026
open
69 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026HighPY_KC-419AOverhaul
23 Sept 2026MediumPX_KC-513KC-513 high vibration
23 Sept 2026MediumPY_KC-419AInspect coupling KC-419A
22 Sept 2026HighPX_KC-536AOverhaul
18 Sept 2026MediumPY_KC-419AInstall scaffolding at KC-419A
11 Sept 2026LowPX_KC-225DKC-225D lube oil filter DP high
07 Sept 2026MediumPX_KC-513Inspect coupling KC-513
05 Sept 2026LowPX_KC-513Inspect coupling KC-513
31 Aug 2026MediumPY_KC-419AInstall cover plate for MCP cracking
30 Aug 2026MediumPX_KC-513KC-513 high vibration

Recent goods issues

Posting dateQtyOrderOrder type
31 May 20251205000010583Other maintenance