COUPLING,SIZE SG630,MONEL
Material 4100010573 · COUPLING · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100010573
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (12 of 14 FuncLocs A/B)
- Supplier
- BERKAH TEKNIK GLOBAL PT
- Lead time
- 100 d · P80 139 d
- Unit price
- Rp 5.3M
Recommendation
- 1.Forecast 6.1 SET/year: 5.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~100 days; expected demand during lead time 1.5.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 12.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 12 now.
- 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 14 FuncLoc(s), 12 of them criticality A/B.
- 7.ML early warning: 37% probability of demand in the next 90 days.
Proposed purchase requisition
12 SET
Rp 63.4M · order by 01 Oct 2026
Expected arrival ≈ 100 days
Long-leadML early warningConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
12
order qty 5
Service level
99.9%
stockout risk now 67%
Unit price
Rp 5.3M
PO history
ML early warning: 37% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 261 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 14 functional locations
12 with criticality A/B · 17 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 4 | 5 | 1.85 |
| PX_KC-479C DILUTION STEAM COMPRESSOR | A | 1 | 5 | 2.71 |
| PX_KC-447 LUBE OIL COMPRESSOR | A | 1 | 4 | 1.85 |
| PX_KC-464A CONDENSATE BLOWER | A | 1 | 2 | 1.43 |
| PX_KC-801 DEMIN WATER FAN | A | 1 | 2 | 1.43 |
| PX_PP-882A CONDENSATE PUMP | A | 1 | 1 | 0.62 |
| PX_KC-250D PROPYLENE FAN | A | 1 | 0 | 0.57 |
| PX_KC-930C SLOP OIL FAN | A | 1 | 0 | 0.57 |
| PX_PP-1101A REFLUX PUMP | A | 1 | 0 | 0.19 |
| PX_PP-494C METHANE PUMP | B | 1 | 8 | 3.62 |
| PX_PP-1516 METHANOL PUMP | B | 1 | 2 | 0.62 |
| PX_PP-731 BFW PUMP | B | 1 | 1 | 0.19 |
Lead time and procurement
Lead time 100 ± 54 days (PO history + category, 2 PO lines) · on-time 31%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Apr 2026 | PR06 Regular replenishment | 1 | Rp 5.2M | 13 Jul 2026 | 77 d |
| 25 May 2025 | PR06 Regular replenishment | 2 | Rp 5.4M | 05 Nov 2025 | 164 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Jul 2027 | PX_PP-135A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 13 Sept 2026 | Low | PX_KC-730 | Overhaul |
| 10 Sept 2026 | Medium | PX_KC-479C | KC-479C bearing temp high |
| 10 Sept 2026 | Medium | PX_PP-494C | Overhaul PP-494C |
| 18 Aug 2026 | Low | PX_KC-479C | Leak from packing |
| 17 Aug 2026 | Medium | PX_KC-447 | Leak from packing |
| 28 Jul 2026 | High | PX_PP-494C | Replace lamp as per PM finding |
| 14 Jul 2026 | Medium | PX_KC-730 | Leak from packing |
| 07 Jul 2026 | Medium | PX_KC-447 | Replace lamp as per PM finding |
| 02 Jul 2026 | High | PX_KC-222B | Replace lamp as per PM finding |
| 31 May 2026 | Medium | PX_KC-479C | [MSI-B-26-KNK-222/M] Replace line |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 13 Jan 2026 | 2 | 201000014126 | Corrective |
| 07 Jan 2026 | 1 | 206000027736 | Other maintenance |
| 23 Nov 2025 | 1 | 201000034542 | Corrective |