Sparely
DU

COUPLING,MODEL FV78,MONEL

Material 4100010668 · COUPLING · Plant 1000

AReduceNon-moving
Material
4100010668
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 6 FuncLocs A/B)
Supplier
No PO history
Lead time
86 d · P80 139 d
Unit price
Rp 8.6M (est.)

Recommendation

  • 1.Forecast 1.0 SET/year: 0.3 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~86 days; expected demand during lead time 0.1.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 3.
  • 4.Stock 15 exceeds the level to keep (3) by 12.
  • 5.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
Convert to Stock ItemPrice estimatedLead time estimated
On hand / on order
15 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
3
order qty 2
Service level
99.8%
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 267.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 6 functional locations

4 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-854C
FEED FAN
A172.28
PX_KC-713B
SPENT CAUSTIC FAN
A163.14
PX_PP-583B
WASH WATER PUMP
A100.19
PX_PP-615A
PROPYLENE PUMP
B100.19
PX_PP-1898A
INHIBITOR PUMP
C120.62
PX_PP-247B
C3 RECYCLE PUMP
C110.62

Lead time and procurement

Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Jan 2027PX_PP-615APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Sept 2026MediumPX_KC-854COverhaul
29 Jul 2026MediumPX_KC-854CInstall scaffolding at KC-854C
17 Jul 2026LowPX_KC-854CPainting KC-854C
17 Jun 2026LowPX_KC-713BLeak from packing
12 Jun 2026HighPX_KC-713BInspect coupling KC-713B
08 Apr 2026MediumPX_KC-713BInspect coupling KC-713B
13 Mar 2026MediumPX_KC-854CKC-854C bearing temp high
21 Dec 2025HighPX_PP-1898AOverhaul PP-1898A
22 Nov 2025MediumPX_KC-854CKC-854C lube oil filter DP high
13 Oct 2025EmergencyPX_KC-713BLeak from packing

Recent goods issues

Never issued in the 17-month history.