COUPLING,SIZE QT629,PTFE

Material 4100010736 · COUPLING · Plant 1000

ALong-leadMonitorInsurance gap
Material
4100010736
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
A (2 of 6 FuncLocs A/B)
Supplier
LANGIT ELEKTRIK ABADI PT
Lead time
94 d · P80 139 d
Unit price
Rp 19.1M

Recommendation

  • 1.Forecast 0.6 SET/year: 0.6 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~94 days; expected demand during lead time 0.2.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 6 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidateLong-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 15%
Unit price
Rp 19.1M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 13 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 590.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 6 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-223
RECYCLE ETHANE FAN
A100.57
PX_KC-930C
SLOP OIL FAN
A100.57
PX_PP-1470A
METHANE PUMP
C131.05
PX_PP-367A
REFLUX PUMP
C100.19
PX_KC-773A
REFLUX COMPRESSOR
S1259.99
PX_KC-458D
SLOP OIL FAN
S193.14

Lead time and procurement

Lead time 94 ± 54 days (PO history + category, 2 PO lines) · on-time 46%

PR dateTypeQtyUnit priceDeliveryLead time
16 Jul 2025PR06
Regular replenishment
2Rp 19.2M27 Sept 202573 d
04 May 2025PR06
Regular replenishment
2Rp 19.1M19 Sept 2025138 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_PP-1470AReplace lamp as per PM finding
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
19 Sept 2026MediumPX_KC-458DKC-458D lube oil filter DP high
16 Sept 2026LowPX_KC-458DKC-458D lube oil filter DP high
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
23 Aug 2026LowPX_KC-773AKC-773A bearing temp high
10 Aug 2026LowPX_KC-773AKC-773A high vibration
09 Aug 2026MediumPX_KC-773AInspect coupling KC-773A
03 Aug 2026MediumPX_KC-773ALeak from packing
20 Jul 2026MediumPX_KC-773AKC-773A high vibration

Recent goods issues

Never issued in the 17-month history.