COUPLING,SIZE QT629,PTFE
Material 4100010736 · COUPLING · Plant 1000
ALong-leadMonitorInsurance gap
- Material
- 4100010736
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 6 FuncLocs A/B)
- Supplier
- LANGIT ELEKTRIK ABADI PT
- Lead time
- 94 d · P80 139 d
- Unit price
- Rp 19.1M
Recommendation
- 1.Forecast 0.6 SET/year: 0.6 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~94 days; expected demand during lead time 0.2.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 6 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidateLong-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 15%
Unit price
Rp 19.1M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 13 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 590.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 6 functional locations
2 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-223 RECYCLE ETHANE FAN | A | 1 | 0 | 0.57 |
| PX_KC-930C SLOP OIL FAN | A | 1 | 0 | 0.57 |
| PX_PP-1470A METHANE PUMP | C | 1 | 3 | 1.05 |
| PX_PP-367A REFLUX PUMP | C | 1 | 0 | 0.19 |
| PX_KC-773A REFLUX COMPRESSOR | S | 1 | 25 | 9.99 |
| PX_KC-458D SLOP OIL FAN | S | 1 | 9 | 3.14 |
Lead time and procurement
Lead time 94 ± 54 days (PO history + category, 2 PO lines) · on-time 46%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Jul 2025 | PR06 Regular replenishment | 2 | Rp 19.2M | 27 Sept 2025 | 73 d |
| 04 May 2025 | PR06 Regular replenishment | 2 | Rp 19.1M | 19 Sept 2025 | 138 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_PP-1470A | Replace lamp as per PM finding |
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 19 Sept 2026 | Medium | PX_KC-458D | KC-458D lube oil filter DP high |
| 16 Sept 2026 | Low | PX_KC-458D | KC-458D lube oil filter DP high |
| 15 Sept 2026 | Low | PX_KC-773A | Install scaffolding at KC-773A |
| 23 Aug 2026 | Low | PX_KC-773A | KC-773A bearing temp high |
| 10 Aug 2026 | Low | PX_KC-773A | KC-773A high vibration |
| 09 Aug 2026 | Medium | PX_KC-773A | Inspect coupling KC-773A |
| 03 Aug 2026 | Medium | PX_KC-773A | Leak from packing |
| 20 Jul 2026 | Medium | PX_KC-773A | KC-773A high vibration |
Recent goods issues
Never issued in the 17-month history.