Sparely
DU

COUPLING,SIZE JT313,NBR

Material 4100010766 · COUPLING · Plant 1000

AReorderCriticalStockout
Material
4100010766
Category
COUPLING
Base unit
SET
MRP type
Stock Item
Criticality
A (5 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
86 d · P80 139 d
Unit price
Rp 8.6M (est.)

Recommendation

  • 1.Forecast 2.4 SET/year: 2.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~86 days; expected demand during lead time 0.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 7 now.
  • 5.Installed on 5 FuncLoc(s), 5 of them criticality A/B.
Proposed purchase requisition
7 SET
Rp 59.9M · order by 01 Oct 2026
Expected arrival ≈ 86 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
7
order qty 3
Service level
100.0%
stockout risk now 43%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 130 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 5 functional locations

5 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_PP-408B
METHANE PUMP
A141.90
PX_PP-207
INHIBITOR PUMP
A131.47
PX_KC-618B
WASH WATER BLOWER
A100.57
PX_KC-669
DEMIN WATER BLOWER
A100.57

Lead time and procurement

Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
18 Aug 2026LowPX_KC-479CLeak from packing
01 Aug 2026MediumPX_PP-408B[MSI-B-26-NMP-200/M] Replace line
31 May 2026MediumPX_KC-479C[MSI-B-26-KNK-222/M] Replace line
27 May 2026MediumPX_PP-207Leak from packing
11 Feb 2026MediumPX_PP-408BReplace bearing PP-408B
01 Nov 2025MediumPX_PP-207PP-207 abnormal noise
04 Oct 2025LowPX_PP-408BOil leak at PP-408B bearing housing
23 Sept 2025LowPX_KC-479COverhaul
02 Jul 2025LowPX_KC-479CKC-479C bearing temp high

Recent goods issues

Posting dateQtyOrderOrder type
24 May 20261201000036749Corrective