Sparely
DU

COUPLING,MODEL WX810,MONEL

Material 4100010806 · COUPLING · Plant 1000

AMonitorSlow-moving
Material
4100010806
Category
COUPLING
Base unit
SET
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
86 d · P80 139 d
Unit price
Rp 8.6M (est.)

Recommendation

  • 1.Forecast 1.9 SET/year: 1.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~86 days; expected demand during lead time 0.5.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 255 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-137A
C4 PRODUCT COMPRESSOR
A121.43
PX_PP-489A
RICH AMINE PUMP
A100.19
PX_KC-513
WASH WATER BLOWER
S1104.42

Lead time and procurement

Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Sept 2026MediumPX_KC-513KC-513 high vibration
07 Sept 2026MediumPX_KC-513Inspect coupling KC-513
05 Sept 2026LowPX_KC-513Inspect coupling KC-513
30 Aug 2026MediumPX_KC-513KC-513 high vibration
12 Jul 2026MediumPX_KC-513Inspect coupling KC-513
20 Jun 2026MediumPX_KC-513KC-513 bearing temp high
11 May 2026MediumPX_KC-513Leak from packing
28 Feb 2026MediumPX_KC-137AOverhaul
22 Nov 2025MediumPX_KC-513Leak from packing
15 Sept 2025MediumPX_KC-513KC-513 bearing temp high

Recent goods issues

Posting dateQtyOrderOrder type
19 Jan 20261201000005786Corrective