Sparely
DU

COUPLING,SIZE LR162,PTFE

Material 4100010855 · COUPLING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100010855
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 5 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
105 d · P80 167 d
Unit price
Rp 5.8M

Recommendation

  • 1.Forecast 4.6 SET/year: 3.9 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~105 days; expected demand during lead time 1.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 12.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 12 now.
  • 5.Long lead time: 80% of deliveries took up to 167 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
  • 7.ML early warning: 31% probability of demand in the next 90 days.
Proposed purchase requisition
12 SET
Rp 69.3M · order by 01 Oct 2026
Expected arrival ≈ 105 days
Long-leadML early warningConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
12
order qty 4
Service level
100.0%
stockout risk now 43%
Unit price
Rp 5.8M
PO history
ML early warning: 31% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 93 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 5 functional locations

4 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PP-1183A
BFW PUMP
A141.47
PX_PP-1797
CHARGE GAS PUMP
A100.19
PX_KC-284A
WASH WATER COMPRESSOR
B121.43
PX_PP-912
BOTTOM PUMP
B120.62
PX_PP-1892B
GASOLINE PUMP
S131.05

Lead time and procurement

Lead time 105 ± 51 days (PO history, 6 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
12 Jul 2026PR03
Regular replenishment
1Rp 5.7M23 Sept 202673 d
05 Jul 2026PR06
Regular replenishment
2Rp 5.8M19 Sept 202676 d
02 Jul 2026PR06
Regular replenishment
2Rp 5.7M09 Sept 202669 d
22 Nov 2025PR06
Regular replenishment
2Rp 5.8M08 May 2026167 d
26 Aug 2025PR06
Regular replenishment
2Rp 5.7M04 Jan 2026131 d
12 Jun 2025PR06
Regular replenishment
1Rp 6.1M04 Dec 2025175 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PY_PP-1183APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1892BReplace lamp as per PM finding
23 Sept 2026MediumPX_PP-1892BPP-1892B abnormal noise
27 Aug 2026MediumPY_PP-1183AReplace lamp as per PM finding
16 Jul 2026MediumPX_PP-912Replace bearing PP-912
13 Jan 2026LowPY_PP-1183APP-1183A abnormal noise
04 Jan 2026MediumPY_PP-1183AInstall scaffolding at PP-1183A
04 Sept 2025MediumPX_KC-284AKC-284A lube oil filter DP high
04 Aug 2025MediumPY_PP-1183APP-1183A seal leak
08 Jul 2025MediumPX_KC-284AKC-284A high vibration
11 May 2025MediumPX_PP-1892BPP-1892B abnormal noise

Recent goods issues

Posting dateQtyOrderOrder type
30 Jun 20262201000006875Corrective
30 Jun 20261201000006875Corrective
25 Feb 20261201000037695Corrective