COUPLING,TYPE AR741,SS316

Material 4100010899 · COUPLING · Plant 1000

BMonitorInsurance gap
Material
4100010899
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
B (2 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
86 d · P80 139 d
Unit price
Rp 8.6M (est.)

Recommendation

  • 1.Forecast 0.2 SET/year: 0.2 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~86 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 4%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 42.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~44 days.

Installed on 3 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-679B
METHANOL PUMP
B271.90
PX_PP-1309C
LUBE OIL PUMP
B320.62
PX_PP-1872A
QUENCH WATER PUMP
S141.90

Lead time and procurement

Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-679BOverhaul PP-679B
20 Sept 2026MediumPX_PP-679BPP-679B seal leak
28 Aug 2026MediumPX_PP-1309C[MSI-B-26-HPD-155] Permanent repair
25 Aug 2026MediumPX_PP-1872AOil leak at PP-1872A bearing housing
22 Aug 2026MediumPX_PP-679BPP-679B high vibration
19 Jul 2026MediumPX_PP-679BInstall scaffolding at PP-679B
29 Apr 2026MediumPX_PP-1872APP-1872A discharge pressure low
22 Dec 2025MediumPX_PP-679BOverhaul PP-679B
28 Oct 2025MediumPX_PP-679BInstall scaffolding at PP-679B
17 Sept 2025LowPX_PP-1872AReplace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.