COUPLING,MODEL PJ969,VITON
Material 4100011015 · COUPLING · Plant 1000
AReduceNon-moving
- Material
- 4100011015
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 86 d · P80 139 d
- Unit price
- Rp 8.6M (est.)
Recommendation
- 1.Forecast 0.2 SET/year: 0.2 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~86 days; expected demand during lead time 0.1.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Stock 7 exceeds the level to keep (2) by 5.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
7 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 231.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 3 functional locations
2 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_KC-419A PROPYLENE FAN | A | 1 | 19 | 5.71 |
| PX_PP-1782B LUBE OIL PUMP | B | 1 | 1 | 0.19 |
| PX_PP-1758A QUENCH OIL PUMP | C | 3 | 0 | 0.19 |
Lead time and procurement
Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | High | PY_KC-419A | Overhaul |
| 23 Sept 2026 | Medium | PY_KC-419A | Inspect coupling KC-419A |
| 18 Sept 2026 | Medium | PY_KC-419A | Install scaffolding at KC-419A |
| 31 Aug 2026 | Medium | PY_KC-419A | Install cover plate for MCP cracking |
| 28 Aug 2026 | Medium | PY_KC-419A | Install scaffolding at KC-419A |
| 12 Aug 2026 | High | PY_KC-419A | KC-419A lube oil filter DP high |
| 11 Jul 2026 | Medium | PY_KC-419A | KC-419A lube oil filter DP high |
| 09 Jul 2026 | Medium | PY_KC-419A | Install scaffolding at KC-419A |
| 09 Mar 2026 | Medium | PY_KC-419A | Install scaffolding at KC-419A |
| 22 Jan 2026 | Low | PY_KC-419A | Inspect coupling KC-419A |
Recent goods issues
Never issued in the 17-month history.