COUPLING,MODEL MD159,SS316

Material 4100011052 · COUPLING · Plant 1000

SReducePotentially obsolete
Material
4100011052
Category
COUPLING
Base unit
SET
MRP type
Stock Item
Criticality
S (0 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
86 d · P80 139 d
Unit price
Rp 8.6M (est.)

Recommendation

  • 1.Forecast 0.3 SET/year: 0.3 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~86 days; expected demand during lead time 0.1.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 55 exceeds the level to keep (0) by 55.
Convert to Non StockPrice estimatedLead time estimated
On hand / on order
55 / 0
no open PO
Today Min / Max
10 / 28
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 683,793/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~44 days.

Installed on 2 functional locations

0 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-582B
CAUSTIC BLOWER
S4103.57
PX_KC-879A
CONDENSATE FAN
S162.71

Lead time and procurement

Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
07 Sept 2026MediumPX_KC-879AReplace lamp as per PM finding
01 Sept 2026HighPX_KC-582BKC-582B high vibration
26 Aug 2026LowPX_KC-582BPainting KC-582B
08 Jul 2026LowPX_KC-582BInstall scaffolding at KC-582B
10 Jun 2026MediumPX_KC-879A[MSI-B-26-PWM-186/M] Replace line
15 May 2026MediumPX_KC-879AOverhaul
28 Apr 2026HighPX_KC-582BKC-582B lube oil filter DP high
20 Apr 2026EmergencyPX_KC-582BRepair insulation KC-582B
05 Jan 2026HighPX_KC-879AReplace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.