COUPLING,TYPE LD756,A105
Material 4100011250 · COUPLING · Plant 1000
AReduceNon-moving
- Material
- 4100011250
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (3 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 86 d · P80 139 d
- Unit price
- Rp 8.6M (est.)
Recommendation
- 1.Forecast 0.2 SET/year: 0.2 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~86 days; expected demand during lead time 0.1.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Stock 25 exceeds the level to keep (2) by 23.
- 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
25 / 0
no open PO
Today Min / Max
10 / 27
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 8.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 213.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 3 functional locations
3 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-536A LUBE OIL BLOWER | A | 1 | 11 | 4.42 |
| PX_KC-435A FUEL OIL AIR COMPRESSOR | A | 1 | 2 | 1.00 |
| PX_PP-1733A RICH AMINE PUMP | B | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 86 ± 54 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | High | PX_KC-536A | Overhaul |
| 08 Aug 2026 | High | PX_KC-536A | KC-536A bearing temp high |
| 24 Jul 2026 | High | PX_KC-536A | Install scaffolding at KC-536A |
| 05 Jul 2026 | Medium | PX_KC-536A | Leak from packing |
| 24 Jun 2026 | Medium | PX_KC-536A | KC-536A bearing temp high |
| 31 Mar 2026 | Medium | PX_KC-536A | Install scaffolding at KC-536A |
| 18 Jan 2026 | Low | PX_KC-536A | Replace lamp as per PM finding |
| 10 Jan 2026 | Low | PX_KC-536A | KC-536A bearing temp high |
| 17 Nov 2025 | Medium | PX_KC-536A | Overhaul |
| 16 Nov 2025 | Medium | PX_KC-435A | Overhaul |
Recent goods issues
Never issued in the 17-month history.