Sparely
DU

COUPLING,MODEL CF785,PTFE

Material 4100011307 · COUPLING · Plant 1000

BLong-leadMaintainCritical insurance spare
Material
4100011307
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
80 d · P80 139 d
Unit price
Rp 8.4M

Recommendation

  • 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~80 days; expected demand during lead time 0.0.
  • 3.A 98.7% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
1 / 1
next delivery 23 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.7%
stockout risk now 0%
Unit price
Rp 8.4M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 14.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~44 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-473A
CONDENSATE PUMP
B161.47

Lead time and procurement

Lead time 80 ± 54 days (PO history + category, 2 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
21 Sept 2026PR04
Regular (other)
1Rp 8.5M23 Nov 2026
open
63 d
28 Jan 2026PR01
Import / long-lead
2Rp 8.3M15 Apr 202677 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Sept 2026MediumPX_PP-473APainting PP-473A
12 Feb 2026MediumPX_PP-473APP-473A abnormal noise
21 Nov 2025MediumPX_PP-473AOverhaul PP-473A
04 Oct 2025LowPX_PP-473AInstall scaffolding at PP-473A
03 Sept 2025MediumPX_PP-473APP-473A seal leak
04 May 2025MediumPX_PP-473AOil leak at PP-473A bearing housing

Recent goods issues

Never issued in the 17-month history.