Sparely
DU

COUPLING,SIZE XL932,A105

Material 4100011480 · COUPLING · Plant 1000

BLong-leadReorderCriticalStockout
Material
4100011480
Category
COUPLING
Base unit
SET
MRP type
Non Stock
Criticality
B (2 of 2 FuncLocs A/B)
Supplier
DUTA ENERGI ABADI PT
Lead time
98 d · P80 124 d
Unit price
Rp 2.7M

Recommendation

  • 1.Forecast 1.7 SET/year: 1.7 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~98 days; expected demand during lead time 0.5.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.On hand 0 + on order 2 is at or below the reorder point: order 3 now.
  • 5.Long lead time: 80% of deliveries took up to 124 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
3 SET
Rp 8.2M · order by 01 Oct 2026
Expected arrival ≈ 98 days
Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 26 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.9%
stockout risk now 1%
Unit price
Rp 2.7M
PO history
ML early warning: 23% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 222 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 396.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~44 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1678A
METHANE PUMP
B110.19
PX_PP-1939
BFW PUMP
B100.19

Lead time and procurement

Lead time 98 ± 39 days (PO history, 3 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
21 Jul 2026PR06
Regular replenishment
2Rp 2.6M26 Nov 2026
open
128 d
21 Apr 2026PR05
Project / turnaround
2Rp 2.7M16 Aug 2026117 d
22 Aug 2025PR06
Regular replenishment
1Rp 2.8M12 Nov 202582 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 May 2025LowPX_PP-1678AOverhaul PP-1678A

Recent goods issues

Posting dateQtyOrderOrder type
21 Feb 20261201000032205Corrective
24 Jan 20261201000029638Corrective
23 Jan 20261201000029638Corrective
12 Dec 20251201000012757Corrective
Sparely