COUPLING,SIZE MZ77,MONEL
Material 4100011527 · COUPLING · Plant 1000
ALong-leadReduceNon-moving
- Material
- 4100011527
- Category
- COUPLING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- PRIMA ELEKTRIK ABADI PT
- Lead time
- 99 d · P80 139 d
- Unit price
- Rp 16.6M
Recommendation
- 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~99 days; expected demand during lead time 0.0.
- 3.A 98.0% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Stock 4 exceeds the level to keep (1) by 3.
- 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
4 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.0%
stockout risk now 0%
Unit price
Rp 16.6M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 70.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 1 | 5 | 1.85 |
Lead time and procurement
Lead time 99 ± 54 days (PO history + category, 1 PO lines) · on-time 30%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 25 Jun 2025 | PR06 Regular replenishment | 1 | Rp 16.6M | 10 Nov 2025 | 138 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 02 Jul 2026 | High | PX_KC-222B | Replace lamp as per PM finding |
| 05 Feb 2026 | Medium | PX_KC-222B | Install scaffolding at KC-222B |
| 01 Jan 2026 | Low | PX_KC-222B | KC-222B high vibration |
| 16 Nov 2025 | Medium | PX_KC-222B | KC-222B lube oil filter DP high |
| 17 May 2025 | Low | PX_KC-222B | Install scaffolding at KC-222B |
Recent goods issues
Never issued in the 17-month history.