COUPLING,SIZE NF728,NBR

Material 4100011605 · COUPLING · Plant 1000

BLong-leadReduceNon-moving
Material
4100011605
Category
COUPLING
Base unit
SET
MRP type
Stock Item
Criticality
B (1 of 2 FuncLocs A/B)
Supplier
ANUGRAH INSTRUMEN SENTOSA PT
Lead time
78 d · P80 139 d
Unit price
Rp 14.3M

Recommendation

  • 1.Forecast 0.2 SET/year: 0.2 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~78 days; expected demand during lead time 0.0.
  • 3.A 95.7% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Stock 173 exceeds the level to keep (1) by 172.
  • 5.Long lead time: 80% of deliveries took up to 139 days and the fastest seen in its category 44 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
173 / 0
no open PO
Today Min / Max
4 / 7
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
95.7%
stockout risk now 0%
Unit price
Rp 14.3M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 48.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~44 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-350A
REFLUX PUMP
B120.19
PX_KC-538
REFLUX BLOWER
S1124.85

Lead time and procurement

Lead time 78 ± 54 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
25 Jul 2025PR03
Regular replenishment
1Rp 14.3M17 Sept 202554 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026EmergencyPX_KC-538KC-538 high vibration
16 Sept 2026EmergencyPX_KC-538Leak from packing
01 Sept 2026MediumPX_KC-538KC-538 lube oil filter DP high
01 Sept 2026MediumPX_KC-538KC-538 high vibration
11 Jun 2026MediumPX_KC-538Leak from packing
05 Jun 2026MediumPX_PP-350AInstall scaffolding at PP-350A
07 May 2026MediumPX_KC-538KC-538 bearing temp high
12 Apr 2026MediumPX_KC-538KC-538 high vibration
04 Apr 2026MediumPX_KC-538Leak from packing
30 Mar 2026MediumPX_KC-538KC-538 high vibration

Recent goods issues

Never issued in the 17-month history.